FIR01-00298
| INSP-Alarm Testing | 9/24/2002 | 9/25/2002 | 9/25/2002 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 09/24/2002 at 10:17:08. Contact: ###-####. one strobe not working in engineering 9/25/2002 9:48:39 AM
|
FIR02-00225
| INSP-Alarm Testing | 9/24/2002 | 9/25/2002 | 9/25/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 09/24/2002 at 10:18:25. Contact: ###-####.
|
FIR02-00251
| INSP-Alarm Testing | 9/24/2002 | 9/25/2002 | 9/25/2002 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 09/24/2002 at 10:19:28. Contact: ###-####. need plans; alarms in this space working - attended fire drill 9/25/2002 9:48:21 AM
|
FIR02-00302
| INSP-Alarm Testing | 9/24/2002 | 9/25/2002 | 9/25/2002 12:00:00 AM | A | PASS |
|
|
###-####
|
FIR02-00371
| INSP-Sprinkler Rough-in | 9/24/2002 | 9/25/2002 | 9/25/2002 12:00:00 AM | A | FAIL |
|
|
overhead; Phone #: ###-#### Internet Inspection Request from: Amy Lawson work per scope of permit not completed; told GC to complete the work or apply for new permit due to many changes with walls, etc for new tenant 9/25/2002 4:04:55 PM
|
FIR02-00302
| INSP-Final Inspection | 9/25/2002 | 9/25/2002 | 9/25/2002 12:00:00 AM | A | PASS |
|
|
|
FIR02-00225
| INSP-Final Inspection | 9/25/2002 | 9/25/2002 | 9/25/2002 12:00:00 AM | A | PASS |
|
|
|
FIR02-00102
| INSP-Sprinkler Rough-in/Hydro | 9/25/2002 | 9/25/2002 | 9/25/2002 12:00:00 AM | P | PART |
|
|
eric- ###-#### hydro okay; need additional EQ on main at south end 46 feet 9/25/2002 2:08:35 PM
|
FIR02-00102
| INSP-Final Inspection | 9/25/2002 | 9/25/2002 | 9/25/2002 12:00:00 AM | P | FAIL |
|
|
eric ###-#### need additional EQ at main on south end 46 feet 9/25/2002 2:09:19 PM
|