Inspections for the day of: Friday, September 25, 2009.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR09-00466 INSP-Conference9/25/20099/25/20099/29/2009 2:25:30 PMPDONE
As-builts have been picked up. Permit finaled.
FIR09-00533 INSP-Final Inspection9/25/20099/25/20099/25/2009 3:50:38 PMPPASS
Permit finaled.
FIR09-00533 INSP-Alarm Testing9/24/20099/25/20099/25/2009 3:50:11 PMPPASS
Permit finaled.
FIR09-00150 INSP-Final Inspection9/24/20099/25/20099/25/2009 3:24:40 PMACANC
Overbooked. Contacted David .
BLD09-01309 FIRE-Final Inspection9/25/20099/25/20099/25/2009 3:21:46 PMPFAIL
There was no access to the tenant to perform the inspection. I left a message on Matt's phone.
FIR09-00291 INSP-Sprinkler Rough-in/Hydro9/25/20099/25/20099/25/2009 2:25:08 PMPPASS
The sprinkler coverage in the deli area has been modified as requested and now the sprinkler piping can be covered.
FIR09-00423 INSP-Final Inspection9/24/20099/25/20099/25/2009 2:24:20 PMAFAIL
The hood suppression system functioned correctly but it has not been connected to the facp so signal verification could not be verified and the piping and appliance layout on the plans does not match the actual installation.
BLD09-01479 FIRE-Final Inspection9/23/20099/25/20099/25/2009 12:29:46 PMAFAIL
See the city approved plans for redlined corrections that include the installation of exit signs, emergency lights and exit discharge lights as well as door hardware issues.
FIR09-00333 INSP-Final Inspection9/23/20099/25/20099/25/2009 12:28:43 PMAFAIL
The city approved sprinkler plans were not on site for the inspection. No inspection was performed.
FIR07-01031 INSP-Sprinkler Rough-in9/24/20099/25/20099/25/2009 11:34:54 AMAPASS
See the city approved plans for piping locations ok to cover.
FIR09-00331 INSP-Sprinkler Rough-in9/24/20099/25/20099/25/2009 11:34:31 AMAPASS
See the city approved plans for piping locations ok to cover.