BLD12-01595
| BLD-Energy code compliance | 9/25/2012 | 9/25/2012 | 9/26/2012 7:43:33 AM | P | PASS |
|
|
steve Phone #: ###-####. rigid foam insulation, interior side of stemwall under slab on grade.
|
BLD12-01594
| BLD-Energy code compliance | 9/25/2012 | 9/25/2012 | 9/26/2012 7:43:17 AM | P | PASS |
|
|
steve Phone #: ###-####. rigid foam insulation, interior side of stemwall under slab on grade.
|
BLD12-01593
| BLD-Energy code compliance | 9/25/2012 | 9/25/2012 | 9/26/2012 7:42:59 AM | P | PASS |
|
|
steve Phone #: ###-####. rigid foam insulation, interior side of stemwall under slab on grade.
|
BLD12-01592
| BLD-Energy code compliance | 9/25/2012 | 9/25/2012 | 9/26/2012 7:42:39 AM | P | PASS |
|
|
steve Phone #: ###-####. rigid foam insulation, interior side of stemwall under slab on grade.
|
BLD12-01603
| BLD-Energy code compliance | 9/25/2012 | 9/25/2012 | 9/26/2012 7:42:22 AM | P | PASS |
|
|
steve Phone #: ###-####. rigid foam insulation, interior side of stemwall under slab on grade.
|
BLD12-01602
| BLD-Energy code compliance | 9/25/2012 | 9/25/2012 | 9/26/2012 7:42:04 AM | P | PASS |
|
|
steve Phone #: ###-####. rigid foam insulation, interior side of stemwall under slab on grade.
|
BLD12-01601
| BLD-Energy code compliance | 9/25/2012 | 9/25/2012 | 9/26/2012 7:41:47 AM | P | PASS |
|
|
steve Phone #: ###-####. rigid foam insulation, interior side of stemwall under slab on grade.
|
BLD12-01600
| BLD-Energy code compliance | 9/25/2012 | 9/25/2012 | 9/26/2012 7:40:53 AM | P | PASS |
|
|
steve Phone #: ###-####. Rigid foam insulation, interior side of stemwall under slab on grade.
|
BLD12-01789
| BLD-Framing/Rough-in | 9/24/2012 | 9/25/2012 | 9/25/2012 3:25:00 PM | P | PART |
|
|
Rich Overland Phone #: ###-####. INterior steel stud framed walls from gridline 10 to 14.9.
|
ESC11-00506
| Site Final | 9/25/2012 | 9/25/2012 | 9/25/2012 2:28:13 PM | P | DONE |
|
|
|
ESC11-00506
| DOC - Permit Finaled | 9/25/2012 | 9/25/2012 | 9/25/2012 2:28:06 PM | P | PASS |
|
|
|
BLD11-01714
| BLD-Final | 9/25/2012 | 9/25/2012 | 9/25/2012 2:27:56 PM | P | FAIL |
|
|
Brett Phone #: ###-####. Provide blower door test results and listed 20 min. door.
|
BLD12-01598
| BLD-Other | 9/25/2012 | 9/25/2012 | 9/25/2012 2:06:27 PM | P | DONE |
|
|
reveiw fire wall construction Phone #: ###-#### >> Inspection requested via web by James Larkin
|
GCB12-00075
| GCB-Final | 9/24/2012 | 9/25/2012 | 9/25/2012 10:03:07 AM | A | FAIL |
|
|
Chi @ ###-#### Call for access. Needs to provide the required energy cert and post. Also provide the blower door test results and post or the 3rd. party airseal inspection report done at framing stage. Correction notice was posted.
|
GCB12-00103
| GCB-Fndatn/slab ins/fld vent | 9/24/2012 | 9/25/2012 | 9/25/2012 9:38:14 AM | A | PASS |
|
|
Marty @ ###-#### Call in advance
|
GCB12-00117
| GCB-Fndatn/slab ins/fld vent | 9/24/2012 | 9/25/2012 | 9/25/2012 9:10:14 AM | A | NR |
|
|
Ryan @ ###-####. No one on site. Footing forms forms still in place, stemwall forms not yet constructed. Will need to reschedule.
|