Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC18-04559 Final9/19/20189/25/20189/25/2018 4:05:42 PMPNR
Field super; Chad Robertson Phone #: ###-#### Inspection requested via web by Lisa Whitney- the scheduled time to install the furnace was changed to 9/26/18- nothing to inspect at this time
MEC18-04465 Final9/21/20189/25/20189/25/2018 3:50:34 PMPPASS
Phone #: ###-#### Inspection requested via web by Mary LaFayette- corrections ok- furnace only co ok
MEC17-04521 Final9/21/20189/25/20189/25/2018 3:46:05 PMPPASS
Jack- you called me on this house. we finally were able to schedule with the homeowner for work to be completed between 3pm-5pm on tuesday the 25th. she does want all this done in one trip from the both of us if possible. i can call you when we are heading that way to get this finished finally. call mike ###-#### if you have questoins. thank you! Phone #: ###-#### Inspection requested via web by Aaron Alandt
-final ok
MEC18-04425 Rough-in9/24/20189/25/20189/25/2018 3:38:28 PMPFAIL
Call Stan prior to going by there ###-####
- Need to provide test evidence that there enough air flow across the smoke detector in it current postion or install the smoke detector in a conventional way on the outside of the duct work so the sample tubes are in the air stream. You will also have to install fire rated access doors in the ceiling next to the smoke detectors
MEC18-03970 Final9/25/20189/25/20189/25/2018 2:49:01 PMPPASS
final - call cyrus Phone #: ###-#### Inspection requested via web by Brandon Sorensen- final ok- card signed
MEC18-03463 Final9/24/20189/25/20189/25/2018 2:36:08 PMPNH
Please call us when you are on your way so we can call customer per request. Thank you! Inspection requested via web by Dan McFate- called and no answer and no access
MEC18-04616 Pressure Test9/25/20189/25/20189/25/2018 2:14:37 PMPPASS
Inspection requested via web by Floyd Floyd Peek- 5lb flue test ok- 20 lb gas test ok- tagged meter
MEC18-04642 Final9/25/20189/25/20189/25/2018 1:41:32 PMPNR
Joseph ###-#### Phone #: ###-#### Inspection requested via web by Krista Boss- need to remove exisiting water flue out of return plemun and re route- furnace and co ok
MEC18-03664 Rough-in9/24/20189/25/20189/25/2018 12:17:38 PMAPART
Phone #: ###-#### Inspection requested via web by Nicholas Paige- duct work insulation ok- still need to see light test on grease duct- not completely sure what needed to be seen on this R/I tried calling foreman
MEC18-04631 Rough-in9/24/20189/25/20189/25/2018 11:56:33 AMANR
Inspection requested via web by Floyd Floyd Peek- need man J- 20lb gas pressure not holding- need to see inertbtape on gas line- supply plenum needs insulated- support line set-
MEC18-03919 Rough-in9/24/20189/25/20189/25/2018 11:38:54 AMAFAIL
Can you call me to make sure I am here amd can we also scheduale it for mid morning please.

This is for the remainimg rough-in inspection and a gas pressure test.
Troy should have the approval on the Manual J in the morning.
The flue test has already been done and the walk through on the house.


Thank you Phone #: ###-#### Inspection requested via web by Geff Blecha
need b vent clearances- need a double valve open ended tee in gas line for pressure test or discconect gas line from meter
MEC18-03332 Final9/24/20189/25/20189/25/2018 10:49:38 AMAPASS
I will send you pics this AM of the fuse we changed. Can you final from picture? Phone #: ###-#### Inspection requested via web by Mary LaFayette- A/C fuse sizes ok- final ok
MEC18-04503 Final9/19/20189/25/20189/25/2018 10:48:24 AMAPASS
Please call Randy Hall prior to inspection. ###-#### Phone #: ###-#### Inspection requested via web by Mary LaFayette- electric furnace only ok
MEC18-04616 Pressure Test9/24/20189/25/20189/25/2018 10:20:02 AMACANC
Inspection requested via web by Floyd Floyd Peek- rescheduled for PM
MEC18-03273 Final9/24/20189/25/20189/25/2018 8:38:11 AMAPASS
AC:2018 Phone #: ###-#### Inspection requested via web by Gary Reeves- line set penetration ok - final ok
MEC18-04538 Final9/24/20189/25/20189/25/2018 8:20:51 AMAPASS
Customer is elderly so it takes her a minute to get to the door. She will be home. Phone #: ###-#### Inspection requested via web by Dan McFate- co detectors ok- final ok
MEC18-03970 Final9/24/20189/25/20189/25/2018 8:09:32 AMANR
final - call cyrus
Phone #: ###-#### Inspection requested via web by Brandon Sorensen- not ready refrigeration lines going through the roof need sealed- arma flex needs UV protection- penetrations in cooler box need sealed- call in for PM when finished
MEC17-03221 Mec-Aging Inspection9/25/20189/25/20189/25/2018 7:46:22 AM CANC
MEC17-03322 Mec-Aging Inspection9/25/20189/25/20189/25/2018 7:46:10 AM CANC