Inspections for the day of: Wednesday, September 26, 2001.
Number of inspections: 20
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorCarl Dependahl
TitleBLD-COM/RES INSPECTOR
Phone #794-9492
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD01-02025 BLD-Aging Inspection9/26/20019/26/20019/26/2001 12:00:00 AM NR
Wip 9/26/2001 8:58:38 AM
BLD00-02242 BLD-Aging Inspection9/26/20019/26/20019/26/2001 12:00:00 AM PART
Wip...plan modified, ok. 9/26/2001 8:29:26 AM
BLD01-01434 BLD-Aging Inspection9/26/20019/26/20019/26/2001 12:00:00 AM NR
wip 9/26/2001 8:58:50 AM
BLD01-01742 BLD-Aging Inspection9/26/20019/26/20019/26/2001 12:00:00 AM NR
roof, no call expires 12-27-01 9/26/2001 1:13:32 PM
BLD01-01204 BLD-Framing/Rough-in9/25/20019/26/20019/26/2001 12:00:00 AMAPART
###-#### ceiling grid over music rm ok pend elec. 9/26/2001 4:34:45 PM
BLD01-00208 BLD-Final9/25/20019/26/20019/26/2001 12:00:00 AMAPASS
Scheduled by a contractor via Hello! on 09/25/2001 at 15:03:22. Contact: ###-####... 9/26/2001 3:36:34 PM c/n ok, card to owner. 9/26/2001 4:14:08 PM
BLD01-00843 BLD-Wall cover9/25/20019/26/20019/26/2001 12:00:00 AMAFAIL
Scheduled by a contractor via Hello! on 09/25/2001 at 15:39:31. Contact: ###-####. c/n re shafts, col's not protected, corridor wall const; obtain complete hvac r/i ok. 9/26/2001 3:31:20 PM
MEC01-02680 Final9/25/20019/26/20019/26/2001 12:00:00 AMAPASS
###-#### ED c/n ok 9/26/2001 12:01:10 PM
BLD01-00893 BLD-Final9/25/20019/26/20019/26/2001 12:00:00 AMAFAIL
dennis- ###-#### fn...c/n, stairs, rails, other finals. do not occupy 9/26/2001 11:55:11 AM
BLD01-01540 BLD-Conference9/26/20019/26/20019/26/2001 12:00:00 AMAPASS
Added by Inspector: 340 On 9/26/2001 8:57:18 AM w/ supt re c/n...need bars at r. rms as shown per ADA
BLD01-02326 BLD-Conference9/26/20019/26/20019/26/2001 12:00:00 AMAPASS
Added by Inspector: 340 On 9/26/2001 9:45:53 AM w/ bldr re landings, hvac, etc.
BLD00-02891 BLD-Conference9/26/20019/26/20019/26/2001 12:00:00 AMAPART
Added by Inspector: 340 On 9/26/2001 11:56:43 AM w/ const foreman...work also for bld01-00893. c/n for final issued w/ that permit
BLD01-00594 BLD-Conference9/26/20019/26/20019/26/2001 12:00:00 AMPPASS
Added by Inspector: 340 On 9/26/2001 2:00:29 PM w/ Bob Peters, eng'r: need documentation for shear walls justifying configuration...shear at 189plf exceeds code allowed for single ply gyp per t-25-s. rejected prior letter, keep c/n.
BLD01-02394 BLD-Conference9/26/20019/26/20019/26/2001 12:00:00 AMPPART
Added by Inspector: 340 On 9/26/2001 3:32:28 PM w/ bld 01-00893, need eng's affidavit/approval for seismic upgrade
BLD01-00553 BLD-Final9/26/20019/26/20019/26/2001 12:00:00 AMPPASS
Added by Inspector: 340 On 9/26/2001 4:15:12 PM ok for l/c, glazing completed.
BLD01-00362 BLD-Final9/26/20019/26/20019/26/2001 12:00:00 AMPPASS
Added by Inspector: 340 On 9/26/2001 4:16:41 PM wall ok for l/c
BLD01-02096 BLD-Framing/Rough-in9/25/20019/26/20019/26/2001 12:00:00 AMPFAIL
fr jill ###-####; c/n stairs, straps, other r/i's. ok to insul. 9/26/2001 5:26:38 PM
MEC01-02877 Final9/25/20019/26/20019/26/2001 12:00:00 AMPCANC
joe ###-#### is homeowner -call 1st before insp--cancel per thomas/mls
BLD00-03538 BLD-Concrete9/25/20019/26/20019/26/2001 12:00:00 AMPPART
Scheduled by a contractor via Hello! on 09/25/2001 at 17:33:26. Contact: ###-####. mcalvaine at parking struct; pt deck under spec insp...masonry? 9/26/2001 3:33:21 PM
BLD01-01540 BLD-Final9/26/20019/26/20019/26/2001 12:00:00 AMPPART
Scheduled by a contractor via Hello! on 09/26/2001 at 07:32:14. Contact: ###-####....keep c/n, ok for t/o, wip. 9/26/2001 3:33:51 PM