FIR05-00872
| FIR-Aging Inspection | 9/26/2006 | 9/26/2006 | 10/3/2006 11:13:28 AM | | DONE |
|
|
Notified contractor to schedule inspection.
|
BLD06-01827
| FIRE-Conference | 9/25/2006 | 9/26/2006 | 9/26/2006 4:07:48 PM | A | DEFR |
|
|
Inspection rescheduled.
|
FIR06-00384
| INSP-Final Inspection | 9/26/2006 | 9/26/2006 | 9/26/2006 3:32:49 PM | P | PASS |
|
|
Fire alarm permit finaled.
|
BLD05-00317
| FIRE-Conference | 9/26/2006 | 9/26/2006 | 9/26/2006 3:28:59 PM | P | DONE |
|
|
On site confrence to discuss exit signage and door hardware at two locations in the sw corner of the building.
|
FIR06-00384
| INSP-Alarm Testing | 9/26/2006 | 9/26/2006 | 9/26/2006 2:37:14 PM | P | PASS |
|
|
Fire alarm work passed field inspection.
|
MIS06-00253
| FIR-Final | 9/25/2006 | 9/26/2006 | 9/26/2006 2:33:49 PM | A | PASS |
|
|
Life safety is satisfactory, inspection passed.
|
FIR06-00376
| INSP-Sprinkler Rough-in/Hydro | 9/20/2006 | 9/26/2006 | 9/26/2006 1:08:08 PM | A | PART |
|
|
Tested notification devices for the basement, 1st floor and mezzanine levels, need to replace two strobe only with horn/strobes as the decible level is too low in one area as discussed, tested vesda systems for zones 1-4, tested two duct detectors for zone 5 and one sd for door hold open at the main level. Concluded inspection at this time due to time constraints, basement detection and new h/s to be verified at next visit.
|
FIR06-00496
| INSP-Sprinkler Rough-in | 9/25/2006 | 9/26/2006 | 9/26/2006 10:52:56 AM | A | PART |
|
|
OH sprinkler rough-in is good for cover at the hard lid ceiling areas only.
|
FIR06-00384
| INSP-Alarm Testing | 9/25/2006 | 9/26/2006 | 9/26/2006 10:31:06 AM | A | DEFR |
|
|
Duplicate inspection request.
|