Inspections for the day of: Monday, September 26, 2016.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorRock A. Hudson
TitleELE-INSPECTOR
Phone #794-6794
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE16-03085 Final9/26/20169/26/20169/26/2016 2:32:49 PMPPASS
I will be down tomorrow to drop in a typed panel schedule. current one is hand written. Thank You- Steve Phone #: ###-#### Inspection requested via web by Steve Blackmer Final ok
ELE16-03085 Electrical Rough-In9/26/20169/26/20169/26/2016 2:32:35 PMPPASS
I will be down tomorrow to drop in a typed panel schedule. current one is hand written. Thank You- Steve Phone #: ###-#### Inspection requested via web by Steve Blackmer
Listing confirmed and rough in ok
ELE16-02800 Permanent Service9/26/20169/26/20169/26/2016 2:31:45 PMPCANC
###-#### Need service inspection
Owner called and asked to cancel until 9-27-16.
ELE15-00495 Electrical Rough-In9/26/20169/26/20169/26/2016 2:27:57 PMPPASS
Ceiling cover for South East soffit can lights over entry ramps on Capitol Street. Contact is Mark Gibson ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves
Soffit and entrance to parking garage ramp as noted on print rough in ok cover
ELE14-03316 Electrical Rough-In9/26/20169/26/20169/26/2016 1:43:23 PMPPASS
Call Brandon for Heat trace rough in basement PLumbing and Fire Sprinkler piping. Phone #: ###-#### Inspection requested via web by Tom Betty
About 1/2 heat trace installed without end caps or starter kits for testing. Rough in ok cover
ELE16-02800 Electrical Rough-In9/26/20169/26/20169/26/2016 1:03:42 PMPFAIL
Phone #: ###-#### Inspection requested via web by Thomas Jenkins
Building permit has not been issued yet. Electrical contractor to call in when building permit has been issued.
ELE16-00151 Electrical Rough-In9/26/20169/26/20169/26/2016 11:56:36 AMAFAIL
Pre TCO walk. Contact is Toby Groves ###-####. Phone #: ###-#### Inspection requested via web by Toby Groves
Too many for formal notes.
Exit ramp wall lights not complete.
Complete fire pack mech. rm ceiling.
Lighting not complete east bus loop.
Covers required for all boxes low volt.
Complete lighting on bus entry ramp.
J-box covers south end and electrical rm.
Bath occ sensors and can lamps.
Server room s/l MC jacket broken.
Service receptacle required 35' ofN. ACs.
Verify all fusing for AC units.
Low volt box open on VRT main level entry.
ELE16-03103 Rough-In Permanent Service9/23/20169/26/20169/26/2016 9:12:22 AMANR
Inspection requested via web by Alan Lusk Pocket doors not set yet and wiring stubbed for these areas. Soffit to build in master stool. OK to foam seal. Will recall when ready
ELE16-02243 Final9/22/20169/26/20169/26/2016 8:34:53 AMAPASS
Install flag mounted sign reading Owyhee Tavern. All Primary Power by others Phone #: ###-#### Inspection requested via web by Ken Olsen
Disconnect and listing confirmed. Final ok
ELE15-01348 Final9/24/20169/26/20169/24/2016 3:00:00 PMACANC
Level5 C@S Branch Circuit Panels, Lighting and Power Outlets, Equip. Conn. Phone #: ###-#### >> Inspection requested via web by Tom Betty Inspection cancelled from web by: Tom Betty
ELE16-01838 Final9/24/20169/26/20169/24/2016 2:59:49 PMACANC
Level 5 TI Power and Lighting, Equip. conn., Office Furniture, All outlets Phone #: ###-#### >> Inspection requested via web by Tom Betty Inspection cancelled from web by: Tom Betty