FIR11-00483
| INSP-Sprinkler Rough-in | 9/27/2011 | 9/27/2011 | 9/28/2011 7:19:10 AM | P | PASS |
|
|
Underground cover inspection passed. Piping can be covered.
|
BLD11-02263
| FIRE-Final Inspection | 9/27/2011 | 9/27/2011 | 9/27/2011 2:56:21 PM | P | FAIL |
|
|
See the city approved plans for a list of corrections. They include a separate permit for sprinkler modifications, annual inspection tag for the fire extinguisher, providing address and removing the thumbturn lock on the exit door.
|
FIR11-00464
| INSP-Sprinkler Rough-in/Hydro | 9/26/2011 | 9/27/2011 | 9/27/2011 2:29:33 PM | A | PASS |
|
|
The underground hydro test passed.
|
FIR11-00498
| INSP-Final Inspection | 9/26/2011 | 9/27/2011 | 9/27/2011 2:28:48 PM | A | FAIL |
|
|
Everything functioned except the lights under the hood did not shut off when the system activated.
|
BLD10-02666
| FIRE-Conference | 9/26/2011 | 9/27/2011 | 9/27/2011 12:08:14 PM | A | DONE |
|
|
I discussed the installation of insulation in the combustible concealed spaces with the insulation contractor.
|
FIR11-00332
| INSP-Sprinkler Rough-in | 9/26/2011 | 9/27/2011 | 9/27/2011 12:07:12 PM | A | PASS |
|
|
Overhead rough-in passed. One pendant needs to be relocated in the corridor. Also the bathroom plan shows a door separating the shower from the remaining restroom. If this separation is not installed the combined space will exceed 50 sq. ft and will require sprinkler protection.
|
FIR11-00490
| INSP-Sprinkler Rough-in | 9/26/2011 | 9/27/2011 | 9/27/2011 12:03:29 PM | A | PASS |
|
|
Sprinkler piping is ok to cover.
|
BLD09-00832
| FIRE-Final Inspection | 9/23/2011 | 9/27/2011 | 9/27/2011 12:00:00 AM | A | CANC |
|
|
Jesse Phone #: ###-####
|