NAF17-00061
| INSP-Final | 9/27/2018 | 9/27/2018 | 10/1/2018 7:29:48 AM | P | FAIL |
|
|
Items 3, 4, 5, 9 and 10 still need corrected. Inspection was left open in hopes that it could be finaled after hours if issues had been resolved.
Phone #: 2088613810 >> Inspection requested via mobile web by Nacho
|
FIR18-00547
| INSP-Sprinkler Rough-in | 9/26/2018 | 9/27/2018 | 9/27/2018 1:26:35 PM | A | PASS |
|
|
The remaining sprinkler piping is ok for cover.
rick Phone #: ###-####
|
FIR18-00414
| INSP-Sprinkler Rough-in | 9/26/2018 | 9/27/2018 | 9/27/2018 1:26:05 PM | A | PART |
|
|
See the city approved plans for locations marked "ok" in red where piping is ok to cover except where earth quake bracing is. All other areas can not be covered. The earth quake bracing material used is not what has been submitted/calculated and in some locations has not been installed in the spot as shown on plans. New calculations are required to be approved including new bracing locations. There are several overhead doors that exceed 4' when in the open position that will require sprinkler coverage beneath them. There are atleast two raisede metal work platforms that may require sprinkler coverage beneath. Earth quake bracing is missing from the 2 1/2" branchlines. Also one area the heads are overspaced.
I stopped the inspection after the above items had been noted so this list is not all inclusive of possible correction items.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00414
| INSP-Sprinkler Rough-in/Hydro | 9/26/2018 | 9/27/2018 | 9/27/2018 12:38:18 PM | A | FAIL |
|
|
Overhead hydro test on both systems failed due to a visible loss on both guages
Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00642
| INSP-Conference | 9/26/2018 | 9/27/2018 | 9/27/2018 12:35:38 PM | A | DONE |
|
|
We dicussed obstructions to the strobes in the Store Room areas.
As early as possible Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price
|
NAF17-00061
| INSP-Final | 9/26/2018 | 9/27/2018 | 9/27/2018 10:11:59 AM | A | FAIL |
|
|
1. As per plan reviewer comment the "Oxygen 107" shall meet IFC 5306.2.2 2. The security doors shall meet IFC 1010.1.9.6 get building code and fire code official approval. 3.Provide revised plans that show "Hall 122" exterior exit door being deleted and the exit sign at the double doors at "Hall 122". 4. Provide approval that locked gates at the east and west exits can remain. 5. Finish roadway and fire dept access. 6. Provide exit discharge light at west exit door. 7. Provide final for hood suppressioni permit. 8. Provide CO2 detection in Riser Room and at fire place. 9. Provide exit sign/exit discharge light as shown in the Dining Room and approved hardware. 10. Provide verification employees and visitors will be provided with exit door code.
Call prior to going Phone #: 2088613810 >> Inspection requested via mobile web by Nacho
|
NAF18-00068
| INSP-Final | 9/25/2018 | 9/27/2018 | 9/27/2018 9:43:12 AM | A | DONE |
|
|
Permit finaled
Call prior to going Phone #: 2089196887 >> Inspection requested via mobile web by Derek
|
NAF18-00112
| INSP-Final | 9/25/2018 | 9/27/2018 | 9/27/2018 9:31:36 AM | A | CANC |
|
|
Call Zach ###-#### >> Inspection requested via web by Don Kartchner Inspection cancelled from web by: Don Kartchner
|