BLD15-01721
| FIRE-Conference | 9/28/2016 | 9/28/2016 | 9/28/2016 4:35:16 PM | P | DONE |
|
|
Fire conference complete, items needed for life fire safety inspection reviewed.
|
BLD15-01721
| FIRE-Final Inspection | 9/27/2016 | 9/28/2016 | 9/28/2016 4:33:43 PM | P | CANC |
|
|
Inspection request was for a fire conference, project is not ready for life fire safety final.
|
FIR16-00265
| INSP-Sprinkler Rough-in | 9/27/2016 | 9/28/2016 | 9/28/2016 4:32:26 PM | P | PASS |
|
|
24 hour air test for dry systems locared in the VRT section complete. Rough to cover inspection for all overhead fire sprinkler piping located VRT complete, all overhead fire sprinkler piping located in VRT approved for cover.
|
FIR16-00146
| INSP-Sprinkler Rough-in/Hydro | 9/27/2016 | 9/28/2016 | 9/28/2016 4:30:43 PM | P | PASS |
|
|
200 psi hydrostatic test for overhead fire sprinkler on levels 8 and 9 complete.
|
FIR13-00167
| INSP-Sprinkler Rough-in/Hydro | 9/27/2016 | 9/28/2016 | 9/28/2016 4:29:56 PM | P | PASS |
|
|
Rough in inspection for overhead fire sprinkler piping garage dry system 5 complete. 200 psi hydrostatic test for garage dry systems 5 and 7 complete
|
FIR16-00100
| INSP-Sprinkler Rough-in/Hydro | 9/27/2016 | 9/28/2016 | 9/28/2016 11:52:27 AM | A | PART |
|
|
200 psi hydrostatic test for overhead fire sprinkler piping complete. Rough in inspection for overhead fire sprinkler piping complete. 24 hour air test started at 11:00AM 28SEPT2016 with 40psi on gauge.
|
BLD15-02982
| FIRE-Final Inspection | 9/28/2016 | 9/28/2016 | 9/28/2016 11:49:54 AM | P | PASS |
|
|
Previously noted items have been repaired/addressed. No fire sprinklers, no fire alarms, fire extinguishers is in place with current inspection tag. Final life fire safey inspection passed/complete.
|
FIR16-00569
| INSP-Sprinkler Rough-in | 9/28/2016 | 9/28/2016 | 9/28/2016 11:14:51 AM | P | PASS |
|
|
Rough to cover inspection for fire sprinkler piping located above hardlids in restroom and soffits in dining area complete, overhead fire sprinkler piping in noted area's approved for cover.
|
BLD16-03245
| FIRE-Final Inspection | 9/27/2016 | 9/28/2016 | 9/28/2016 10:46:02 AM | A | CANC |
|
|
Inspection request cancelled per conversation with Greg Phone #: ###-####, inspection will rescheduled for a later date.
|