Inspections for the day of: Tuesday, September 3, 2002.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorRuss Owen
TitleBLD-COM/RES INSPECTOR
Phone #794-9473
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD02-01209 BLD-Final8/30/20029/3/20029/3/2002 12:00:00 AMAFAIL
Scheduled by a contractor via Hello! on 08/30/2002 at 11:32:39. Contact: ###-####.
BLD02-00396 BLD-Final8/30/20029/3/20029/3/2002 12:00:00 AMAPASS
###-####
MEC02-02435 Rough-in8/30/20029/3/20029/3/2002 12:00:00 AMAFAIL
Scheduled by a contractor via Hello! on 08/30/2002 at 17:30:46. Contact: ###-####.c/n. 9/3/2002 4:21:28 PM
MEC02-02435 Pressure Test8/30/20029/3/20029/3/2002 12:00:00 AMAFAIL
Scheduled by a contractor via Hello! on 08/30/2002 at 17:31:10. Contact: ###-####.
BLD02-02025 BLD-Framing/Rough-in9/3/20029/3/20029/3/2002 12:00:00 AMPFAIL
paul; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie. Needs engineers field report and energy seal 9/3/2002 4:27:26 PM no inspectins done c/n posted. 9/3/2002 4:27:57 PM
BLD02-01209 BLD-Final9/3/20029/3/20029/3/2002 12:00:00 AMPPASS
###-#### key at front outlet
BLD02-01942 BLD-Footing9/3/20029/3/20029/3/2002 12:00:00 AMPFAIL
needs 24 in. 9/3/2002 4:24:06 PM
BLD02-00489 BLD-Footing8/30/20029/3/20029/3/2002 12:00:00 AMPPART
late late pm ###-####ok pending s-i. 9/3/2002 4:24:24 PM
BLD02-01028 BLD-Wall cover8/29/20029/3/20029/3/2002 12:00:00 AMPPART
Scheduled by a contractor via Hello! on 08/29/2002 at 08:41:08. Contact: ###-####. need draft stops and roof starps added below ceiling contractor on site will recall all of which are prior c/ns. 9/3/2002 4:29:00 PM
BLD02-01225 BLD-Framing/Rough-in8/30/20029/3/20029/3/2002 12:00:00 AMPPART
Scheduled by a contractor via Hello! on 08/30/2002 at 10:36:39. Contact: ###-####. ceiling ok. 9/3/2002 4:24:43 PM