ELE99-03436
| Electrical Rough-In | 9/29/1999 | 9/30/1999 | 9/30/1999 12:00:00 AM | A | PASS |
|
|
MIKE-- PAGER ###-#### --RE-INSP R/I (JMS) r/I ok
|
ELE99-03090
| Electrical Rough-In | 9/29/1999 | 9/30/1999 | 9/30/1999 12:00:00 AM | A | PART |
|
|
Jesse ###-#### (JMS) ok
|
ELE99-03467
| Final | 9/29/1999 | 9/30/1999 | 9/30/1999 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 09/29/1999 at 15:27:43. Contact: ###-####. R/I p/s u/g new ok
|
ELE99-03447
| Final | 9/29/1999 | 9/30/1999 | 9/30/1999 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 09/29/1999 at 16:23:36. Contact: ###-####. (JMS) called cor. Posted b.c.c. meter too high, and needs connector for remex in j box ( old panel )
|
ELE99-01760
| Electrical Rough-In | 9/29/1999 | 9/30/1999 | 9/30/1999 12:00:00 AM | A | PART |
|
|
Judith ###-####; underground (JMS) (Pat gave ok to cover some underground already) r/I for u/g ok
|
ELE99-02773
| Rough-In Permanent Service | 9/27/1999 | 9/30/1999 | 9/30/1999 12:00:00 AM | A | PASS |
|
|
EMMETT ###-#### 16 ROOMS A/C 200 AMPS p/s u/g and r/I
|
ELE99-03103
| Electrical Rough-In | 9/28/1999 | 9/30/1999 | 9/30/1999 12:00:00 AM | P | PART |
|
|
steve-- ###-#### r/i r/I ok with Del & Paul
|
ELE99-03492
| Rough-In Permanent Service | 9/30/1999 | 9/30/1999 | 9/30/1999 12:00:00 AM | P | PASS |
|
|
BERNICE ###-#### 16 ROOMS A/C 100 AMPS r/I & p/s u/g new ok
|
ELE99-03407
| Temporary Service | 9/30/1999 | 9/30/1999 | 9/30/1999 12:00:00 AM | P | NR |
|
|
SKIP--###-#### RE-INSP TEMP POLE---ALREADY HAD AN INSP????? Trench not ready
|
ELE99-02609
| Final | 9/30/1999 | 9/30/1999 | 9/30/1999 12:00:00 AM | P | FAIL |
|
|
late pm please partial final barry ###-#### low voltage not supported properly
|
ELE99-03007
| Final | 9/30/1999 | 9/30/1999 | 9/30/1999 12:00:00 AM | P | FAIL |
|
|
rick ###-#### called needs to install master bed closet light
|
ELE99-03499
| Final | 9/30/1999 | 9/30/1999 | 9/30/1999 12:00:00 AM | P | PASS |
|
|
Risk ###-#### called rick will install a 18 cu in
|