PLM10-02099
| Final | 9/29/2010 | 9/30/2010 | 9/30/2010 4:31:19 PM | P | PASS |
|
|
robin Phone #: ###-####
|
PLM10-02075
| Storm Drains | 9/30/2010 | 9/30/2010 | 9/30/2010 3:53:22 PM | P | PASS |
|
|
storm drain test ok
|
PLM10-01251
| Roof Drains | 9/30/2010 | 9/30/2010 | 9/30/2010 3:52:35 PM | P | PASS |
|
|
Please call Matt with questions ###-#### Phone #: ###-#### >> Inspection requested via web by Sonja Hankel roof and overflow drain,s test ok
|
PLM10-02090
| Water and/or Sewer | 9/29/2010 | 9/30/2010 | 9/30/2010 1:50:03 PM | P | CANC |
|
|
Main valve and tie in is at the meter and the pvb is next to the house. We ran Schedule 40 pipe from the main valve to the pvb and insured positive drainage back to main valve. Thanks. Phone #: ###-#### >> Inspection requested via web by Clyde Lingo
|
PLM10-02090
| Sprinkler (Final) | 9/30/2010 | 9/30/2010 | 9/30/2010 1:49:51 PM | P | PASS |
|
|
|
MEC10-02978
| Final | 9/29/2010 | 9/30/2010 | 9/30/2010 12:34:11 PM | A | PASS |
|
|
TML will be there all morning, no need to call before going. Thank you! Phone #: ###-#### >> Inspection requested via web by Michele LaMott
|
PLM10-02101
| Groundwork | 9/29/2010 | 9/30/2010 | 9/30/2010 10:23:10 AM | A | PASS |
|
|
ground sewer rough in for mop sink, drinking fountain,and break room sink. building will be open at 9:30 am. I will be there all day thanks Phone #: ###-#### >> Inspection requested via web by Anderson Kenny
|
PLM10-02085
| Water and/or Sewer | 9/29/2010 | 9/30/2010 | 9/30/2010 9:33:00 AM | A | CANC |
|
|
canc. by contractor will recall when ready
|
PLM10-02100
| Plumbing Rough-in | 9/29/2010 | 9/30/2010 | 9/30/2010 9:22:56 AM | A | PASS |
|
|
>> Inspection requested via web by John Hensley
|
PLM10-02100
| DOC - Permit Finaled | 9/30/2010 | 9/30/2010 | 9/30/2010 9:22:45 AM | A | PASS |
|
|
>> Inspection requested via web by John Hensley
|
PLM10-02075
| Storm Drains | 9/30/2010 | 9/30/2010 | 9/30/2010 8:56:25 AM | A | PART |
|
|
visual on piping ok will test at a later date
|