FIR10-00407
| INSP-Sprinkler Rough-in | 9/30/2010 | 9/30/2010 | 10/1/2010 6:26:52 AM | P | PASS |
|
|
The remaining underground supply piping can be covered except for the tie in to the United Water section. This section did not have the thrust blocks poured yet.
|
BLD10-02249
| FIRE-Final Inspection | 9/29/2010 | 9/30/2010 | 9/30/2010 2:56:02 PM | A | FAIL |
|
|
The exit sign/emergency light out the rear exit had not been repaired and the exit discharge light had not been installed.
|
BLD09-01846
| FIRE-Conference | 9/28/2010 | 9/30/2010 | 9/30/2010 2:29:37 PM | A | DONE |
|
|
I've been contacted by both owners who have assured me that Protex has been directed to finish the project and is infact done. I'm currently waiting for the inspection to be called in.
|
BLD09-01324
| FIRE-Conference | 9/28/2010 | 9/30/2010 | 9/30/2010 2:28:49 PM | A | DONE |
|
|
I've been contacted by both owners who have assured me that Protex has been directed to finish the project and is infact done. I'm currently waiting for the inspection to be called in.
|
FIR10-00212
| INSP-Conference | 9/28/2010 | 9/30/2010 | 9/30/2010 2:28:01 PM | A | DONE |
|
|
I've been contacted by both owners who have assured me that Protex has been directed to finish the project and is infact done. I'm currently waiting for the inspection to be called in.
|
BLD10-01582
| FIRE-Final Inspection | 9/29/2010 | 9/30/2010 | 9/30/2010 1:58:01 PM | A | PASS |
|
|
Life safety passed.
|