BLD13-02286 FIRE-Conference9/23/20139/23/2013 P 
Matt phone #: ###-####
FIR13-00495 INSP-Sprinkler Rough-in9/30/20139/30/20139/30/2013 5:08:30 PMPPART
Overhead modifications at the grid ceiling areas okayed for cover. Provide verification calcs will support two heads fed by 1" pipe at the NE corner open office.
FIR13-00170 INSP-Alarm Testing9/30/20139/30/20139/30/2013 5:06:10 PMPNR
Pending noted corrections at building #4
BLD13-01816 FIRE-Final Inspection9/30/20139/30/20139/30/2013 5:05:11 PMPPASS
Life safety inspection passed.
FIR13-00436 INSP-Sprinkler Rough-in/Hydro9/24/20139/30/20139/30/2013 5:04:22 PMAPART
Overhead hydrostatic test completed satisfactory. Also finished rough-in at the high bay sales floor area only- EQ bracing and seismic branchline restraints are not yet finished.
FIR13-00367 INSP-Final Inspection9/27/20139/30/20139/30/2013 5:01:27 PMPPASS
Previous correction items field verified, walkthrough completed. Fire sprinkler permit finaled.
BLD12-01894 FIRE-Final Inspection9/27/20139/30/20139/30/2013 10:56:18 AMAPASS
Corrections verified for completion. Life safety finaled.
BLD12-01893 FIRE-Final Inspection9/27/20139/30/20139/30/2013 10:55:09 AMAPASS
C/N items finished. Life safety passed.
BLD12-02415 FIRE-Final Inspection9/27/20139/30/20139/30/2013 9:52:49 AMAPASS
Remainder of fire life safety inspection items completed and passed.
FIR13-00443 INSP-Final Inspection9/25/20139/30/20139/30/2013 9:36:09 AMAPASS
Functional testing passed. Fire alarm permit final approved.