FIR14-00205
| INSP-Sprinkler Rough-in | 9/30/2014 | 9/30/2014 | 9/30/2014 5:11:29 PM | P | PART |
|
|
UG fire supply line approved for cover from the point of connection at the property line to the building stem wall. *Note- ductile riser and associated thrust block are incomplete at this time. Refer to dated notes on plan.
|
BLD14-01432
| FIRE-Final Inspection | 9/30/2014 | 9/30/2014 | 9/30/2014 1:59:28 PM | P | PASS |
|
|
Life safety inspection passed. PFE and address numbers posted while on site.
|
FIR14-00516
| INSP-Sprinkler Rough-in | 9/29/2014 | 9/30/2014 | 9/30/2014 1:40:06 PM | A | PART |
|
|
Overhead work at the grid ceilings passed rough-in. Need to repair/patch holes at the deck where new hangers are installed. One upright head at the NE corner open gym area needs relocated, also missing coverage at ductwork obstruction NE corner.
|
FIR14-00386
| INSP-Final Inspection | 9/29/2014 | 9/30/2014 | 9/30/2014 1:37:18 PM | A | PASS |
|
|
Correction items completed. Fire sprinkler permit finaled.
|
BLD14-01689
| FIRE-Final Inspection | 9/29/2014 | 9/30/2014 | 9/30/2014 12:13:31 PM | A | PASS |
|
|
Noted correction items verified for completion. Life safety final approved.
|
FIR14-00702
| INSP-Sprinkler Rough-in | 9/29/2014 | 9/30/2014 | 9/30/2014 11:24:53 AM | A | PART |
|
|
Scope of fire sprinkler work approved for cover at the sheetrock lids.
|
FIR14-00669
| INSP-Sprinkler Rough-in | 9/29/2014 | 9/30/2014 | 9/30/2014 10:58:49 AM | A | PART |
|
|
Okay to cover overhead fire sprinkler modifications at the grid ceilings within the tenant remodel area.
|
FIR14-00519
| INSP-Conference | 9/29/2014 | 9/30/2014 | 9/30/2014 10:37:56 AM | A | DONE |
|
|
On site conference with contractor regarding new fire alarm work, duct smoke detection, notification, remote annunciator, knox box, and manual pull stations. Plan modification recommended for proposed changes.
|