NAF15-00006
| INSP-Sprinkler Rough-in/Hydro | 9/30/2015 | 9/30/2015 | 9/30/2015 5:17:03 PM | P | DONE |
|
|
All hydro tests have been previously completed. Walked through north east wing, identified painted heads to be replaced and heads in bathrooms that need to be changed to 175 deg due to proximity to heat source.
Previous item of concern with the unheated patio/storage area and sprinkler head. Contractor added a vent register between living space and patio storage area.
|
NAF15-00014
| INSP-Alarm Testing | 9/30/2015 | 9/30/2015 | 9/30/2015 5:16:53 PM | P | FAIL |
|
|
Verified all devices are correct. Tested four detectors, three worked. Room numbers reported do not match actual marked room numbers. Elevator recall from 1st floor worked. Contractor to fix programing for correct room number identification.
|