Inspections for the day of: Friday, September 4, 2009.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR09-00334 FIR-Aging Inspection9/4/20099/4/20099/10/2009 8:13:48 AM NR
work is in progress per david
FIR08-00830 INSP-Sprinkler Rough-in/Hydro9/3/20099/4/20099/4/2009 4:39:59 PMPPART
The dry pipe riser on the first floor failed the 24 hour air test. The dry pipe riser on the second floor passed the 24 hour air test.
FIR09-00466 INSP-Final Inspection9/3/20099/4/20099/4/2009 1:54:24 PMPFAIL
The city approved job site stamped drawings were not on site. Also as-builts are needed that reflect the actual installation. The as-builts will need to be compared against the copies that I marked up while performing the inspection. One manual pull station needed to be lowered while I waited as well as the candellas adjusted on two ceiling mounted strobes.
FIR09-00455 INSP-Final Inspection9/3/20099/4/20099/4/2009 1:35:16 PMPPASS
Permit finaled.
BLD09-00835 FIRE-Final Inspection9/4/20099/4/20099/4/2009 1:08:15 PMPPART
A temporary for the life safety was given with mark sentennos permission until the two duct smoke detectors have been tested no later than tuesday. This was relayed to the general contractor.
BLD09-01272 FIRE-Final Inspection9/3/20099/4/20099/4/2009 1:02:17 PMAFAIL
Life safety not performed since the project related fire alarm permit was failed.
FIR09-00511 INSP-Final Inspection9/3/20099/4/20099/4/2009 10:59:40 AMAFAIL
The hvac units did not shutdown when the duct smoke detector went into alarm. A re-inspection fee for the next inspection, the third, has been applied.
FIR09-00343 INSP-Final Inspection9/3/20099/4/20099/4/2009 10:00:18 AMAPASS
Permit finaled. The diffuser has been relocated