Inspections for the day of: Thursday, September 4, 2014.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR14-00550 INSP-Final Inspection9/4/20149/4/20149/5/2014 10:04:42 AMPPASS
Permit finaled
FIR14-00552 INSP-Sprinkler Rough-in9/4/20149/4/20149/4/2014 3:40:07 PMPPASS
Underground piping is ok to cover. I notified Tim that the underground loop on the plans is actually 6" not 8". Actual work performed by TVFP is 8".
FIR14-00356 INSP-Sprinkler Rough-in9/4/20149/4/20149/4/2014 2:52:33 PMPPASS
Rough-in passed. Tenting passed. Piping can be covered.
FIR14-00474 INSP-Sprinkler Rough-in9/4/20149/4/20149/4/2014 2:38:22 PMPPASS
See the city approved plans for area clouded in red where rough-in is passed. Noted uprights slightly overspaced in small Storage Room.
FIR14-00325 INSP-Sprinkler Rough-in9/3/20149/4/20149/4/2014 2:37:05 PMPCANC
Wrong permit number called in. Rick Phone #: ###-####
FIR14-00448 INSP-Sprinkler Rough-in9/3/20149/4/20149/4/2014 2:37:01 PMACANC
Cancel per John Phone #: ###-####
FIR14-00339 INSP-Sprinkler Rough-in/Hydro9/3/20149/4/20149/4/2014 2:32:08 PMACANC
Cancel per John Phone #: ###-####
FIR14-00537 INSP-Sprinkler Rough-in/Hydro9/3/20149/4/20149/4/2014 11:11:20 AMACANC
Dry pendant leaking so no hydro today. Will be rescheduled per Matt.
FIR14-00524 INSP-Supply line flush9/3/20149/4/20149/4/2014 11:10:40 AMAPASS
Underground supply line flush passed
FIR14-00613 INSP-Sprinkler Rough-in9/3/20149/4/20149/4/2014 11:10:10 AMAPASS
Rough-in passed piping is ok to cover
FIR14-00356 INSP-Sprinkler Rough-in9/3/20149/4/20149/4/2014 10:03:34 AMAPASS
Piping can be covered.
FIR14-00357 INSP-Sprinkler Rough-in9/3/20149/4/20149/4/2014 9:56:31 AMAPASS
Tenting and piping rough-in passed. Piping can be covered.