FIR14-00550
| INSP-Final Inspection | 9/4/2014 | 9/4/2014 | 9/5/2014 10:04:42 AM | P | PASS |
|
|
Permit finaled
|
FIR14-00552
| INSP-Sprinkler Rough-in | 9/4/2014 | 9/4/2014 | 9/4/2014 3:40:07 PM | P | PASS |
|
|
Underground piping is ok to cover. I notified Tim that the underground loop on the plans is actually 6" not 8". Actual work performed by TVFP is 8".
|
FIR14-00356
| INSP-Sprinkler Rough-in | 9/4/2014 | 9/4/2014 | 9/4/2014 2:52:33 PM | P | PASS |
|
|
Rough-in passed. Tenting passed. Piping can be covered.
|
FIR14-00474
| INSP-Sprinkler Rough-in | 9/4/2014 | 9/4/2014 | 9/4/2014 2:38:22 PM | P | PASS |
|
|
See the city approved plans for area clouded in red where rough-in is passed. Noted uprights slightly overspaced in small Storage Room.
|
FIR14-00325
| INSP-Sprinkler Rough-in | 9/3/2014 | 9/4/2014 | 9/4/2014 2:37:05 PM | P | CANC |
|
|
Wrong permit number called in. Rick Phone #: ###-####
|
FIR14-00448
| INSP-Sprinkler Rough-in | 9/3/2014 | 9/4/2014 | 9/4/2014 2:37:01 PM | A | CANC |
|
|
Cancel per John Phone #: ###-####
|
FIR14-00339
| INSP-Sprinkler Rough-in/Hydro | 9/3/2014 | 9/4/2014 | 9/4/2014 2:32:08 PM | A | CANC |
|
|
Cancel per John Phone #: ###-####
|
FIR14-00537
| INSP-Sprinkler Rough-in/Hydro | 9/3/2014 | 9/4/2014 | 9/4/2014 11:11:20 AM | A | CANC |
|
|
Dry pendant leaking so no hydro today. Will be rescheduled per Matt.
|
FIR14-00524
| INSP-Supply line flush | 9/3/2014 | 9/4/2014 | 9/4/2014 11:10:40 AM | A | PASS |
|
|
Underground supply line flush passed
|
FIR14-00613
| INSP-Sprinkler Rough-in | 9/3/2014 | 9/4/2014 | 9/4/2014 11:10:10 AM | A | PASS |
|
|
Rough-in passed piping is ok to cover
|
FIR14-00356
| INSP-Sprinkler Rough-in | 9/3/2014 | 9/4/2014 | 9/4/2014 10:03:34 AM | A | PASS |
|
|
Piping can be covered.
|
FIR14-00357
| INSP-Sprinkler Rough-in | 9/3/2014 | 9/4/2014 | 9/4/2014 9:56:31 AM | A | PASS |
|
|
Tenting and piping rough-in passed. Piping can be covered.
|