BLD18-03923
| FIRE-Final Inspection | 9/4/2019 | 9/4/2019 | 9/4/2019 3:19:00 PM | P | PASS |
|
|
Life safety passed. Card signed. Brandon Phone #: ###-####
|
FIR19-00653
| INSP-Final Inspection | 9/4/2019 | 9/4/2019 | 9/4/2019 3:18:08 PM | P | FAIL |
|
|
Need to relocate the two manual pull stations to the 10' - 20' min. max. Need shield between fryer and oven. No testing performed. zack Phone #: ###-####
|
BLD18-03121
| FIRE-Final Inspection | 9/3/2019 | 9/4/2019 | 9/4/2019 2:05:22 PM | A | CANC |
|
|
Life safety will be a pass for the north most apartments when the project related fire alarm and fire sprinkler permits are passed. Matt- mid mornign Phone #: ###-####
|
FIR19-00309
| INSP-Final Inspection | 9/3/2019 | 9/4/2019 | 9/4/2019 2:04:32 PM | A | FAIL |
|
|
Today's inspection had it passed would be only for the six north most apartments. However two of the three flow switches did not function. Still need to test the crawl space tamper switches.
Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR19-00203
| INSP-Final Inspection | 9/3/2019 | 9/4/2019 | 9/4/2019 2:01:25 PM | A | FAIL |
|
|
Two fo the three flow switches did not function. Still need to test the crawl space tamper switches.
We would like 9:30am if that is possible. Phone #: ###-#### Inspection requested via web by Fire Scheduler
|
FIR19-00461
| INSP-Final Inspection | 9/3/2019 | 9/4/2019 | 9/4/2019 12:28:18 PM | A | PART |
|
|
A temporary for this permit is being given until an upgrade agreement has been finalized with the Boise Fire Dept for the fire alarm system.
This inspection needs to be before 7:30 am as this is a school and they will be in session. Please call ahead to Brian @ ###-####. Phone #: ###-#### Inspection requested via web by Kristin Dolan
|
NAF19-00074
| INSP-Sprinkler Rough-in/Hydro | 9/3/2019 | 9/4/2019 | 9/4/2019 10:50:07 AM | A | PASS |
|
|
Overhead rough-in, tenting and hydro passed. Piping is ok for cover. Well supply piping not provided yet.
Call prior to going Phone #: 2083910988 >> Inspection requested via mobile web by Anthony Minichiello
|
BLD19-02940
| FIRE-Final Inspection | 9/3/2019 | 9/4/2019 | 9/4/2019 9:27:10 AM | A | PASS |
|
|
life safety passed. Card signed.
ask for Sue // Duane Phone #: ###-####
|
FIR19-00511
| INSP-Sprinkler Rough-in | 9/3/2019 | 9/4/2019 | 9/4/2019 12:00:00 AM | P | PART |
|
|
**Partial Rough Inspection Pass** Inspection of pipe hangers prior to the installation of roof insulation**MAS**
Kenny Caldwell is the contact. This is to be a rough-in hanger inspection. Thank you for your hard work! Phone #: ###-#### >> Inspection requested via web by Stan Beus
|