MIS02-00165
| BLD-Final | 9/4/2002 | 9/5/2002 | 9/5/2002 12:00:00 AM | A | PASS |
|
|
Ben ###-#### call prior to meet there if needed...complaint apparently resolved, mgr repaired windows, etc...no further contact from complaintant/tenant. 9/5/2002 9:21:50 AM
|
BLD02-01720
| BLD-Framing/Rough-in | 9/4/2002 | 9/5/2002 | 9/5/2002 12:00:00 AM | A | PART |
|
|
###-####; braces added at 24" oc, vertical member & redundant ceiling frame ok to delete. eng's letter to follow 9/5/2002 12:15:50 PM
|
BLD02-01822
| BLD-Foundation | 9/4/2002 | 9/5/2002 | 9/5/2002 12:00:00 AM | A | PART |
|
|
Phone #: ###-#### Internet Inspection Request from: Amy Lawson...wall, bar ok. 9/5/2002 12:18:41 PM
|
BLD02-01782
| BLD-Conference | 9/5/2002 | 9/5/2002 | 9/5/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 09/05/2002 at 07:03:06. Contact: ###-####...w/ bldr re finals, corridor const. & ADA clearances. 9/5/2002 2:47:23 PM
|
BLD02-01964
| BLD-Other | 9/5/2002 | 9/5/2002 | 9/5/2002 12:00:00 AM | A | PART |
|
|
comm'l re-roof, WIP ok.
|
BLD02-01833
| BLD-Footing | 9/5/2002 | 9/5/2002 | 9/5/2002 12:00:00 AM | P | NR |
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung plans? 9/6/2002 3:26:20 PM
|
BLD02-01263
| BLD-Final | 9/4/2002 | 9/5/2002 | 9/5/2002 12:00:00 AM | P | NR |
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
|
MEC02-02485
| Pressure Test | 9/5/2002 | 9/5/2002 | 9/5/2002 12:00:00 AM | P | PART |
|
|
###-####...pt ok, secure pipe as needed...fp?? 9/5/2002 7:19:29 PM
|
MEC02-02485
| Rough-in | 9/5/2002 | 9/5/2002 | 9/5/2002 12:00:00 AM | P | FAIL |
|
|
secure gas pipe, complete r/i... 9/5/2002 7:20:14 PM
|
MEC02-01914
| Final | 9/5/2002 | 9/5/2002 | 9/5/2002 12:00:00 AM | P | FAIL |
|
|
###-#### single level house ready for final....c/n, registers, whole hse fan& timer, flue not complete, insufficient bends at flex duct/boots, support line-sets, seal penetrations & boots... $42 reinsp fee due 9/5/2002 6:58:52 PM
|
BLD02-00057
| BLD-Framing/Rough-in | 9/4/2002 | 9/5/2002 | 9/5/2002 12:00:00 AM | P | PART |
|
|
bill ###-####, seismic upgrade, has mti re 9/5/2002 5:25:45 PM ports for welds, epoxy bolting, need eng's ok...looks good. 9/5/2002 5:26:48 PM
|
BLD02-00345
| BLD-Framing/Rough-in | 9/4/2002 | 9/5/2002 | 9/5/2002 12:00:00 AM | P | PART |
|
|
call bill first, pre frame, elec not in; wants to relocate 1st fl rest room, ok w/ ADA dimensions. 9/5/2002 3:53:25 PM
|