BLD02-01263
| FIRE-Final Inspection | 9/4/2002 | 9/5/2002 | 9/5/2002 12:00:00 AM | A | FAIL |
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung need door hardware completed; per Dave Miller a temp occ can be issued if door hardware is completed; alarm plans not submitted as of today; will need to verify duct detectors/ alarms plans for permanent occ 9/5/2002 4:02:48 PM
|
FIR02-00005
| INSP-Sprinkler Rough-in/Hydro | 9/4/2002 | 9/5/2002 | 9/5/2002 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 09/04/2002 at 13:28:58. Contact: ###-####. heads obstructed/overspaced in basement mechanical; refer room; janitor room; EQ branch line in south room; add line and head in south room as shown on plans; heads painted in computer room; heads fire proofed in service corridor; temp walk way off concourse okay to cover; combustibles in concealed space by phone area; okay to cover mechanical chase on third floor 9/5/2002 11:05:16 AM
|
BLD02-00331
| FIRE-Final Inspection | 9/5/2002 | 9/5/2002 | 9/5/2002 12:00:00 AM | P | PASS |
|
|
RON; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
BLD02-01278
| FIRE-Final Inspection | 9/5/2002 | 9/5/2002 | 9/5/2002 12:00:00 AM | P | PASS |
|
|
fire fn rich- ###-####
|