FIR07-00219
| INSP-Final Inspection | 9/5/2007 | 9/5/2007 | 9/5/2007 6:59:09 PM | P | FAIL |
|
|
The 15cd strobe in the office area needs to be changed to atleast a 30cd to meet code spacing requirements. No test performed.
|
BLD06-03513
| FIRE-Final Inspection | 9/4/2007 | 9/5/2007 | 9/5/2007 6:55:34 PM | P | FAIL |
|
|
Need the project related fire alarm and fire sprinkler permits finaled. Also the door hardware out of the corridor needs to have the dead bolt removed.
|
BLD06-02673
| FIRE-Final Inspection | 9/4/2007 | 9/5/2007 | 9/5/2007 6:52:01 PM | P | PASS |
|
|
life safety passed
|
BLD05-00633
| FIRE-Final Inspection | 9/5/2007 | 9/5/2007 | 9/5/2007 1:38:37 PM | P | CANC |
|
|
As stated in the previous entries no life safety inspection will be performed until the related fire alarm and fire sprinkler permits are finaled. No inspection was performed.
|
BLD07-01819
| FIRE-Final Inspection | 9/4/2007 | 9/5/2007 | 9/5/2007 1:35:43 PM | A | CANC |
|
|
Per a phone conversation with the contractor the doors are not installed yet. No inspection was performed.
|
BLD06-01621
| FIRE-Final Inspection | 9/4/2007 | 9/5/2007 | 9/5/2007 1:32:48 PM | A | PASS |
|
|
Life safety passed.
|
FIR06-00957
| INSP-Final Inspection | 9/4/2007 | 9/5/2007 | 9/5/2007 1:31:16 PM | A | FAIL |
|
|
The remaining 3rd floor areas were inspected. The same obstructions as noted yesterday occur in the other third floor areas. There was no access into room 397. A canopy was missing from the bathroom pendant in room 374 and no sprinkler coverage was provided in the corridor electrical closet on the third floor C wing. The items from the previous correction notice still need addressed.
|
FIR06-00956
| INSP-Final Inspection | 9/4/2007 | 9/5/2007 | 9/5/2007 1:30:33 PM | A | FAIL |
|
|
The remaining 3rd floor areas were inspected. The same obstructions as noted yesterday occur in the other third floor areas. There was no access into room 397. A canopy was missing from the bathroom pendant in room 374 and no sprinkler coverage was provided in the corridor electrical closet on the third floor C wing. The items from the previous correction notice still need addressed.
|
FIR06-00958
| INSP-Final Inspection | 9/4/2007 | 9/5/2007 | 9/5/2007 1:29:45 PM | A | FAIL |
|
|
The remaining 3rd floor areas were inspected. The same obstructions as noted yesterday occur in the other third floor areas. There was no access into room 397. A canopy was missing from the bathroom pendant in room 374 and no sprinkler coverage was provided in the corridor electrical closet on the third floor C wing. The items from the previous correction notice still need addressed.
|
BLD07-01532
| FIRE-Final Inspection | 9/4/2007 | 9/5/2007 | 9/5/2007 12:42:01 PM | A | PASS |
|
|
LIfe safety passed
|
BLD07-01764
| FIRE-Final Inspection | 9/4/2007 | 9/5/2007 | 9/5/2007 11:28:44 AM | A | PASS |
|
|
Life safety passed
|
BLD07-01704
| FIRE-Conference | 9/4/2007 | 9/5/2007 | 9/5/2007 10:16:18 AM | A | DONE |
|
|
I went over fire alarm and fire sprinkler requirements with Ivan.
|
FIR06-00178
| INSP-Final Inspection | 8/30/2007 | 9/5/2007 | 9/5/2007 10:05:46 AM | A | FAIL |
|
|
One of the new a/v's in the exam rooms did not function, the existing devices need to be mounted at the code compliant heights as per the city approved drawings and manometer test need to be performed on the duct smoke detectors as requested on the previous correction notice. The duct detector will need to be tested for functionality as well.
|
FIR06-00011
| INSP-Alarm Testing | 9/4/2007 | 9/5/2007 | 9/5/2007 9:58:12 AM | A | DONE |
|
|
I test the remaining firemans phone jacks. Three have not been tested. They are located in the elevator lobbys of the 9th and 4th floors as well as one in the basement emergency generator room. Placards are required to be placed at each of the phone jacks listing location. I notified Brian with Simplex of this. The phone jacks in the elevators have not been connected or tested yet.
|
FIR05-00536
| INSP-Final Inspection | 9/4/2007 | 9/5/2007 | 9/5/2007 9:52:15 AM | A | DONE |
|
|
The basement and first floors of the central tower are basically ready for final. The basement has a couple of small issues. In a shower a cabinet has been installed and is blocking sprinkler coverage and in the east stairwell a hanger has been removed and the head under the stairs still has tape on it.
|