Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR11-00052 FIR-Aging Inspection9/5/20129/5/20129/5/2012 6:58:25 PM DEFR
FIR09-00443 FIR-Aging Inspection9/5/20129/5/20129/5/2012 6:58:10 PM DEFR
FIR10-00329 FIR-Aging Inspection9/5/20129/5/20129/5/2012 6:57:54 PM DEFR
FIR12-00291 INSP-Alarm Testing9/5/20129/5/20129/5/2012 6:57:36 PMPPART
Regarding fire door operations and releasing mechanism per NFPA 80.
BLD12-01426 FIRE-Sprinkler Rough-in9/5/20129/5/20129/5/2012 6:54:16 PMPPART
Overhead fire sprinkler work approved for cover at the drop ceilings.
BLD12-01425 FIRE-Sprinkler Rough-in9/5/20129/5/20129/5/2012 6:53:14 PMPPART
Okay to cover overhead fire sprinkler work.
BLD12-02247 FIRE-Final Inspection9/4/20129/5/20129/5/2012 1:30:55 PMAPASS
Correction items field verified for completion. Life safety passed.
BLD12-02273 FIRE-Conference9/4/20129/5/20129/5/2012 12:56:24 PMADONE
On site visit regarding fire sprinkler coverage at the new office to meet NFPA 13 guidelines. Discussed the "small room rule" spacing and ft2 conditions.
BLD12-01977 FIRE-Conference9/5/20129/5/20129/5/2012 12:53:45 PMADONE
On site discussion with contractor regarding fire life safety inspection items, exit sign locations, an existing roll up fire door to be disabled provided documentation of approval is aquired.
BLD12-00764 FIRE-Final Inspection9/4/20129/5/20129/5/2012 12:49:26 PMAPASS
Fire life safety inspection completed satisfactory. Noted correction items are finished.
FIR12-00108 INSP-Sprinkler Rough-in9/4/20129/5/20129/4/2012 9:19:11 PMACANC
Rough to Cover 2nd Floor Atrium - Scott Carter is the contact at ###-#### Phone #: ###-#### >> Inspection requested via web by Kindel de Leon Inspection cancelled from web by: Scott Carter II