MIS18-00303
| BLD-Conference | 8/16/2018 | 8/30/2018 | | A | |
|
|
Check on status. Issue fivee day notice if needed.
|
MIS18-00304
| BLD-Conference | 8/16/2018 | 8/30/2018 | | A | |
|
|
Check on status. Isue 5 day notice if needed.
|
BLD18-00229
| BLD-Framing/Rough-in | 9/4/2018 | 9/4/2018 | | P | |
|
|
Jerimy Phone #: ###-####
|
BLD18-01160
| BLD-Wall Bracing | 9/5/2018 | 9/5/2018 | 9/5/2018 3:35:10 PM | P | CANC |
|
|
|
BLD16-04475
| BLD-Final | 9/5/2018 | 9/5/2018 | 9/5/2018 3:35:01 PM | P | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by Sam Brown. Complete posting of address.. 20 min. fire door required to be self closing. Window next to shower stall upstairs rquired to be tempered.
|
BLD16-04476
| BLD-Final | 9/5/2018 | 9/5/2018 | 9/5/2018 3:33:05 PM | P | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by Sam Brown. Complete posting of address. 20 min. fire door required to be self closing.
|
BLD16-04346
| BLD-Energy code compliance | 9/4/2018 | 9/5/2018 | 9/5/2018 2:33:58 PM | P | FAIL |
|
|
call 20 mins ahead-Josh Phone #: ###-####. Needs to repair let in bracing.
|
BLD16-04346
| BLD-Framing/Rough-in | 9/4/2018 | 9/5/2018 | 9/5/2018 2:33:20 PM | P | FAIL |
|
|
call 20 mins ahead-Josh Phone #: ###-####. Needs to complete airseal pack.
|
BLD17-04218
| BLD-Final | 9/5/2018 | 9/5/2018 | 9/5/2018 1:50:22 PM | P | PASS |
|
|
Please call Justin 1/2-hour prior to inspection, thank you. Phone #: ###-#### Inspection requested via web by Justin Dauby. All issues have been resolved. Ok for perm occ.
|
BLD18-00573
| BLD-Conference | 9/4/2018 | 9/5/2018 | 9/5/2018 1:43:16 PM | P | DONE |
|
|
Dry wall ceiling is in but walls are not. Insulation is sprayed in the walls but the ceiling has not been done yet. I was wondering, do I need to have an Insulation inspection done before moving to drywall the walls? I will have the ceiling insulation done later this week when Brandon schedules it with his crew. This will be a blow-in insulation and a top off the rest of the house, where needed.
You can just call me if I need to wait for the ceiling (which I assume) but I did not want to wait on the wall drywall unless I had to. just unsure on where my next inspection is. I have the mechanical inspector coming tomorrow for the wood stove and mini split conference, before I get to far on those.
Thanks, Robert Phone #: ###-#### Inspection requested via web by Robert Smith
|
BLD18-00573
| BLD-Framing/Rough-in | 9/5/2018 | 9/5/2018 | 9/5/2018 1:43:07 PM | P | PASS |
|
|
Dry wall ceiling is in but walls are not. Insulation is sprayed in the walls but the ceiling has not been done yet. I was wondering, do I need to have an Insulation inspection done before moving to drywall the walls? I will have the ceiling insulation done later this week when Brandon schedules it with his crew. This will be a blow-in insulation and a top off the rest of the house, where needed.
You can just call me if I need to wait for the ceiling (which I assume) but I did not want to wait on the wall drywall unless I had to. just unsure on where my next inspection is. I have the mechanical inspector coming tomorrow for the wood stove and mini split conference, before I get to far on those.
Thanks, Robert Phone #: ###-#### Inspection requested via web by Robert Smith
|
BLD18-01160
| BLD-Framing/Rough-in | 9/4/2018 | 9/5/2018 | 9/5/2018 11:06:00 AM | A | NR |
|
|
Jeff Phone #: ###-####. Need wall beracing plan from engineer.
|
BLD16-04475
| BLD-Blower Door Test Results | 9/5/2018 | 9/5/2018 | 9/5/2018 10:41:07 AM | P | DONE |
|
|
5.6ACH @50pa.
|
BLD18-02847
| BLD-Final | 9/4/2018 | 9/5/2018 | 9/5/2018 10:16:04 AM | A | FAIL |
|
|
call 15 mins ahead- Jackie Phone #: ###-####. Glazing around interior patio and back patio are required to be tempered. Correction notice was isued.
|
BLD18-02936
| BLD-Final | 9/4/2018 | 9/5/2018 | 9/5/2018 8:44:54 AM | A | PASS |
|
|
Clarisse Phone #: ###-####
|
BLD18-02936
| DOC - Permit Finaled | 9/5/2018 | 9/5/2018 | 9/5/2018 8:44:46 AM | P | PASS |
|
|
|
BLD18-02116
| BLD-Framing/Rough-in | 9/4/2018 | 9/5/2018 | 9/5/2018 8:28:46 AM | A | PASS |
|
|
Eric Phone #: ###-####. Verified install and nailing of STHD14 hold downs prior to cover.
|