MEC00-02346
| Pressure Test | 9/5/2000 | 9/6/2000 | 9/6/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 09/05/2000 at 16:39:58. Contact: ###-####.
|
MEC00-02903
| Final | 9/5/2000 | 9/6/2000 | 9/6/2000 12:00:00 AM | A | PASS |
|
|
Gary ###-####...done by tony 9/6/2000 12:08:53 PM
|
MEC00-02930
| Rough-in | 9/5/2000 | 9/6/2000 | 9/6/2000 12:00:00 AM | A | NR |
|
|
Scheduled by a contractor via Hello! on 09/05/2000 at 11:33:24. Contact: ###-####.
|
MEC00-02977
| Rough-in | 9/5/2000 | 9/6/2000 | 9/6/2000 12:00:00 AM | A | NR |
|
|
Scheduled by a contractor via Hello! on 09/05/2000 at 11:37:28. Contact: ###-####.
|
MEC00-02977
| Pressure Test | 9/5/2000 | 9/6/2000 | 9/6/2000 12:00:00 AM | A | NR |
|
|
Scheduled by a contractor via Hello! on 09/05/2000 at 11:37:48. Contact: ###-####.
|
MEC00-01765
| Final | 9/5/2000 | 9/6/2000 | 9/6/2000 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 09/05/2000 at 14:49:36. Contact: ###-####.
|
MEC00-02884
| Final | 9/1/2000 | 9/6/2000 | 9/6/2000 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 09/01/2000 at 12:03:33. Contact: ###-####...need comb air 9/6/2000 10:37:05 AM
|
MEC00-02973
| Rough-in | 9/1/2000 | 9/6/2000 | 9/6/2000 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 09/01/2000 at 16:10:28. Contact: ###-####....no f/p set 9/6/2000 2:30:50 PM
|
MEC99-04303
| Final | 9/5/2000 | 9/6/2000 | 9/6/2000 12:00:00 AM | P | PASS |
|
|
larry 867- 6096 fn
|
MEC00-02970
| Final | 9/5/2000 | 9/6/2000 | 9/6/2000 12:00:00 AM | P | NR |
|
|
Scheduled by a contractor via Hello! on 09/05/2000 at 16:28:14. Contact: ###-####...shawna will recall 9/6/2000 12:39:13 PM
|
MEC00-02601
| Final | 9/6/2000 | 9/6/2000 | 9/6/2000 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 09/06/2000 at 08:06:50. Contact: ###-####.
|
MEC00-02961
| Rough-in | 9/6/2000 | 9/6/2000 | 9/6/2000 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 09/06/2000 at 08:08:08. Contact: ###-####.
|
MEC00-02984
| Final | 9/6/2000 | 9/6/2000 | 9/6/2000 12:00:00 AM | P | PASS |
|
|
fn-- ###-####- hammonds
|
MEC00-01909
| Final | 9/6/2000 | 9/6/2000 | 9/6/2000 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 09/06/2000 at 09:01:11. Contact: ###-####.
|
MEC99-04303
| Final | 9/6/2000 | 9/6/2000 | 9/6/2000 12:00:00 AM | P | PASS |
|
|
LARRY ###-#### FN
|
MEC00-02701
| Final | 9/6/2000 | 9/6/2000 | 9/6/2000 12:00:00 AM | P | NR |
|
|
Scheduled by a contractor via Hello! on 09/06/2000 at 10:44:28. Contact: ###-####.
|
MEC00-02980
| Final | 9/6/2000 | 9/6/2000 | 9/6/2000 12:00:00 AM | P | NR |
|
|
April ###-#### furnace and a water heater only....called at 1:00..no answer 9/6/2000 1:01:48 PM
|
MEC00-01396
| Final | 9/6/2000 | 9/6/2000 | 9/6/2000 12:00:00 AM | P | PASS |
|
|
Added by Inspector: 411 On 9/6/2000
|