Inspections for the day of: Wednesday, September 6, 2006.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MIS06-00227 FIR-Final9/5/20069/6/20069/7/2006 9:20:23 AMAPASS
Life safety finaled
FIR06-00257 INSP-Sprinkler Rough-in/Hydro9/6/20069/6/20069/6/2006 4:57:45 PMPPASS
Underground supply piping is ok to bury but there is a potential problem with the bury depth as the piping follows the footings. It actually slope up to the stub-in. The top of pipe is 3'-2" from the top of the footing. I spoke to Brian about this. Final depth will be verifyied once final grade is complete.
FIR05-00536 INSP-Sprinkler Rough-in9/6/20069/6/20069/6/2006 4:55:27 PMPPASS
See the city approved plans for the portion of the 4th floor rough-in that was inspected and passed today
FIR06-00526 INSP-Sprinkler Rough-in/Hydro9/6/20069/6/20069/6/2006 2:55:33 PMPPASS
See the city approved plans for the canopy piping that was inspected.
BLD05-02379 FIRE-Final Inspection9/6/20069/6/20069/6/2006 2:48:04 PMPPASS
Life safety finaled
FIR06-00391 INSP-Final Inspection9/6/20069/6/20069/6/2006 2:47:23 PMPPASS
permit finaled
FIR06-00391 INSP-Alarm Testing9/5/20069/6/20069/6/2006 12:55:41 PMAPASS
Permit finaled
FIR05-00799 INSP-Alarm Testing9/5/20069/6/20069/6/2006 11:52:20 AMADONE
See the city approved plans for devices tested today which included the induct detectors and duct detectors for unit shutdown. Per the mechanical contractor the max cfm in the trunk lines is roughly 1200. The simplex detectors are listed to 2000cfm.