Inspections for the day of: Wednesday, September 6, 2006.
Number of inspections: 25
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAimee Hughes
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC06-00989 BMP Violation9/1/20069/6/20069/6/2006 2:14:13 PMAPEND
9-6-06 Per Steve Webb inspection extended until 9-7-06 on contractor's request.

Written Correction issued to rp; Refer to History. Complete items on c/notice, plan and permit conditions or a stop work may be issued. Status to Steve; Phone #: ###-#### T. D.
ESC05-01165 Tracking Control9/6/20069/6/20069/6/2006 11:51:33 AMPPASS
Site looks okay.
ESC05-01706 Tracking Control9/6/20069/6/20069/6/2006 11:51:04 AMPPASS
Site looks okay.
ESC05-01857 Tracking Control9/6/20069/6/20069/6/2006 11:50:41 AMPPASS
Site looks okay.
ESC05-00714 Site Final9/6/20069/6/20069/6/2006 11:50:06 AMPPASS
ESC05-01677 Site Final9/6/20069/6/20069/6/2006 11:49:42 AMPPASS
ESC05-00714 Tracking Control9/6/20069/6/20069/6/2006 11:47:35 AMPCANC
ESC04-00760 Site Final9/6/20069/6/20069/6/2006 11:45:50 AMPPASS
ESC05-01271 Site Final9/6/20069/6/20069/6/2006 10:40:12 AMPPASS
Final stabilization has been completed.
ESC05-01307 Site Final9/6/20069/6/20069/6/2006 10:39:46 AMPPASS
Final stabilization has been completed.
ESC05-01793 Site Final9/6/20069/6/20069/6/2006 10:39:20 AMPPASS
Final stabilization has been completed.
ESC05-01275 Site Final9/6/20069/6/20069/6/2006 10:38:20 AMPPASS
Final stabilization has been completed.
ESC05-01281 Site Final9/6/20069/6/20069/6/2006 10:38:02 AMPPASS
Final stabilization has been completed.
ESC05-01280 Tracking Control9/6/20069/6/20069/6/2006 10:37:32 AMPPASS
Site looks good, all bmp's are being maintained.
ESC05-01334 Tracking Control9/6/20069/6/20069/6/2006 10:24:25 AMPPASS
Site looks good.
ESC06-00149 Tracking Control9/5/20069/6/20069/6/2006 10:23:51 AMAPART
Met with RP to discuss new construction entrance being used and making sure that it is properly marked and old construction entrance is blocked off to avoid any trackout onto Gowen rd.
ESC05-01786 Site Final9/6/20069/6/20069/6/2006 10:17:42 AMPPASS
Final stabilization has been completed.
ESC05-01069 Site Final9/6/20069/6/20069/6/2006 10:16:53 AMPPASS
Final stabilization has been completed.
ESC05-01228 Tracking Control9/5/20069/6/20069/6/2006 10:14:11 AMAPASS
Site looks okay, all bmp's are being maintained.
ESC05-01844 Tracking Control9/5/20069/6/20069/6/2006 10:13:34 AMAPASS
Site looks good, all bmp's are being maintained.
ESC05-01844 Tracking Control9/5/20069/6/20069/6/2006 10:12:16 AMACANC
ESC05-01130 Tracking Control9/5/20069/6/20069/6/2006 9:58:37 AMAPART
Met with RP to discuss entrance at base of hill in culdesac. Access control is needed or a construction entrance needs to be installed. RP is meeting with ACHD today to decide ROW issues, he will inform me of outcome of meeting and let me know when or if the access will need to occur at bottom entrance.
ESC05-01130 Tracking Control9/5/20069/6/20069/6/2006 9:35:10 AMACANC
ESC06-00282 Tracking Control9/5/20069/6/20069/6/2006 9:30:12 AMAPASS
Site looks good, all bmp's are being maintained.
ESC06-00211 Tracking Control9/5/20069/6/20069/6/2006 9:27:40 AMAPASS
Site looks okay, talked to RP about keeping up on dust control.