ESC11-00415
| General Inspection | 9/6/2012 | 9/6/2012 | 9/10/2012 1:16:51 PM | | PASS |
|
|
|
ESC12-00270
| Aging Inspection | 9/6/2012 | 9/6/2012 | 9/7/2012 1:48:54 PM | | DONE |
|
|
PErmit finaled.
|
ESC12-00067
| Aging Inspection | 9/6/2012 | 9/6/2012 | 9/6/2012 3:57:25 PM | | PART |
|
|
Meeting with RP tomorrow to discuss over preparing for winter controls.
|
ESC12-00177
| Aging Inspection | 9/6/2012 | 9/6/2012 | 9/6/2012 3:56:42 PM | | PASS |
|
|
|
ESC11-00117
| General Inspection | 9/6/2012 | 9/6/2012 | 9/6/2012 3:56:31 PM | | PASS |
|
|
|
ESC12-00637
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:36:42 AM | A | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00610
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:36:29 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00614
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:36:20 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00609
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:36:11 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00613
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:36:02 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00618
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:35:53 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00612
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:35:44 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00636
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:35:35 AM | A | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00611
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:35:25 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00640
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:35:15 AM | A | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00621
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:35:04 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00635
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:34:55 AM | A | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00616
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:34:45 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00620
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:34:33 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00615
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:34:23 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00619
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:34:13 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00626
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:34:03 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00625
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:33:54 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00630
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:33:43 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00608
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:33:32 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00629
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:33:23 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00623
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:33:11 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00634
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:33:01 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00607
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:32:51 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00633
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:32:41 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00622
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:32:31 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00632
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:32:20 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00617
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:32:10 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00624
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:31:52 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00628
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:31:39 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00631
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:31:28 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00627
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:31:17 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00642
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:21:48 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00638
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:21:36 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00641
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/6/2012 9:21:23 AM | | PART |
|
|
Verbal to RP: Clean up on a daily basis in required to remove all sediment and material off of the hard surfaces.
|
ESC12-00639
| Site Preparation | 8/30/2012 | 9/6/2012 | 9/5/2012 9:54:28 AM | A | PASS |
|
|
|
ESC12-00636
| Site Preparation | 8/30/2012 | 9/6/2012 | 8/30/2012 7:58:33 AM | | NR |
|
|
|