Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC13-00887 Site Preparation9/4/20139/4/2013 P 
jeff Phone #: ###-####
BLD13-01395 BLD-Framing/Rough-in9/5/20139/6/20139/6/2013 4:07:32 PMPPASS
Larry Phone #: ###-####. Recieved engineering for addtional framing for tv suuports off of roof joist. Noted in place construction was found to be acceptable.
BLD13-00525 BLD-Footing9/5/20139/6/20139/6/2013 3:32:41 PMPPASS
Andy Phone #: ###-####. Bldg. foundation ok.
BLD13-00007 BLD-Final9/6/20139/6/20139/6/2013 3:32:07 PMPNR
Please call Nate before walking. No one is currently on-site. I will meet you over there. I will meet you there anytime.. Phone #: ###-#### >> Inspection requested via web by nate hutton
BLD13-01888 BLD-Framing/Rough-in9/5/20139/6/20139/6/2013 1:30:24 PMPPASS
partial r/i -- Chad Phone #: ###-####. Interior wood framed wals for phase 1 ok.
BLD13-01995 BLD-Final9/5/20139/6/20139/6/2013 11:13:38 AMAPASS
Shawn Phone #: ###-####
BLD13-01995 DOC - Permit Finaled9/6/20139/6/20139/6/2013 11:13:06 AMPPASS
fascia connection ok.
BLD13-01725 BLD-Framing/Rough-in9/5/20139/6/20139/6/2013 10:50:11 AMAPASS
Phone #: ###-#### >> Inspection requested via web by Clint Wall
BLD13-01230 BLD-Wall Bracing9/5/20139/6/20139/6/2013 10:13:18 AMAPART
Phone #: 8904657 >> Inspection requested via mobile web by Tyler. Exterior shearwall nailing ok. Need to verifiy all simpson hdu holdowns on framing inspection, not yet installed.
BLD13-02086 BLD-Framing/Rough-in9/5/20139/6/20139/6/2013 9:39:08 AMAPASS
greg Phone #: ###-####
BLD13-02207 BLD-Final9/5/20139/6/20139/6/2013 9:13:10 AMAPASS
As early as possible - Sean Phone #: ###-####. ok for perm occ.
ESC13-00555 General Inspection9/6/20139/6/2013