FIR17-00307
| INSP-Final Inspection | 9/5/2017 | 9/6/2017 | 9/6/2017 2:15:54 PM | P | PASS |
|
|
Permit finaled for the scope of work.
|
BLD16-02899
| FIRE-Conference | 9/6/2017 | 9/6/2017 | 9/6/2017 2:04:34 PM | P | DONE |
|
|
Performed the rest of the life safety today. I need the project related fire alarm pemit finaled, NFPA signs for the oxygen room, provide fire dept access signage at the south entrance.
|
FIR17-00040
| INSP-Final Inspection | 9/5/2017 | 9/6/2017 | 9/6/2017 11:17:18 AM | A | FAIL |
|
|
Need the correct as-builts, map at the facp, test security doors interface, and record of completion.
|
FIR14-00701
| INSP-Final Inspection | 9/5/2017 | 9/6/2017 | 9/6/2017 11:13:52 AM | A | FAIL |
|
|
Not ready for final yet. Today we tested the additional strobe in the short corridor that was added. Hvac unit would not shut down upon activation of the smoke detector.
John Lopez Phone #: ###-####
|