MEC99-02912
| Final | 9/7/1999 | 9/7/1999 | 9/8/1999 12:00:00 AM | P | FAIL |
|
|
sandy ###-#### fn insp; 9/8 C/N issued - called Sandy. jrb;
|
MEC99-02096
| Final | 9/3/1999 | 9/7/1999 | 9/8/1999 12:00:00 AM | P | NH |
|
|
Scheduled by Hello!. Contact phone is [4424130]; 9/8 no access. jrb
|
MEC99-02469
| Final | 9/3/1999 | 9/7/1999 | 9/7/1999 12:00:00 AM | | PASS |
|
|
Scheduled by Hello!. Contact phone is [3751100]; 9/7 entered jrb
|
BLD99-01225
| INSP - Final | 9/3/1999 | 9/7/1999 | 9/7/1999 12:00:00 AM | A | PASS |
|
|
PLEASE CALL DAVE BRUCE, ###-####, SO HE CAN MEET YOU. 9/7 Ok pending fire final. jrb
|
BLD99-01599
| INSP - Foundation | 9/2/1999 | 9/7/1999 | 9/7/1999 12:00:00 AM | A | PASS |
|
|
BRAD ###-####; 9/7 entered jrb
|
BLD99-02626
| INSP - Foundation | 9/3/1999 | 9/7/1999 | 9/7/1999 12:00:00 AM | A | PART |
|
|
###-#### mike ft insp; 9/7 1st of 3 form sets. jrb
|
BLD99-02153
| INSP-Final Inspection | 9/7/1999 | 9/7/1999 | 9/7/1999 12:00:00 AM | P | NR |
|
|
Scheduled by a contractor via Hello! on 09/07/1999 at 10:26:32. Contact: ###-####. 9/7 entered jrb
|
BLD99-01225
| INSP-Final Inspection | 9/7/1999 | 9/7/1999 | 9/7/1999 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 09/07/1999 at 10:49:17. Contact: ###-####.; 9/7 fire ok per 409. jrb;
|
BLD99-01192
| INSP - Foundation | 9/7/1999 | 9/7/1999 | 9/7/1999 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 09/07/1999 at 08:08:22. Contact: ###-####. 9/7 Rebar OK, Ground rod OK. jrb
|
BLD99-02414
| INSP - Final | 9/7/1999 | 9/7/1999 | 9/7/1999 12:00:00 AM | P | FAIL |
|
|
WALT ###-####; 9/7 Engineer req 2x8 #2 of 24 oc, approved plan 2x6 of 240c, provide engineer for 2x6. jrb
|
BLD99-01468
| INSP - Framing/Rough-in | 9/7/1999 | 9/7/1999 | 9/7/1999 12:00:00 AM | P | PASS |
|
|
jason-- ###-#### cell -ceiling insp; Ceiling grid ok for cover. jrb
|