Inspections for the day of: Tuesday, September 7, 1999.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Storey
TitleBLD-COM/RES INSPECTOR
Phone #794-9490
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC99-02912 Final9/7/19999/7/19999/8/1999 12:00:00 AMPFAIL
sandy ###-#### fn insp; 9/8 C/N issued - called Sandy. jrb;
MEC99-02096 Final9/3/19999/7/19999/8/1999 12:00:00 AMPNH
Scheduled by Hello!. Contact phone is [4424130]; 9/8 no access. jrb
MEC99-02469 Final9/3/19999/7/19999/7/1999 12:00:00 AM PASS
Scheduled by Hello!. Contact phone is [3751100]; 9/7 entered jrb
BLD99-01225 INSP - Final9/3/19999/7/19999/7/1999 12:00:00 AMAPASS
PLEASE CALL DAVE BRUCE, ###-####, SO HE CAN MEET YOU. 9/7 Ok pending fire final. jrb
BLD99-01599 INSP - Foundation9/2/19999/7/19999/7/1999 12:00:00 AMAPASS
BRAD ###-####; 9/7 entered jrb
BLD99-02626 INSP - Foundation9/3/19999/7/19999/7/1999 12:00:00 AMAPART
###-#### mike ft insp; 9/7 1st of 3 form sets. jrb
BLD99-02153 INSP-Final Inspection9/7/19999/7/19999/7/1999 12:00:00 AMPNR
Scheduled by a contractor via Hello! on 09/07/1999 at 10:26:32. Contact: ###-####. 9/7 entered jrb
BLD99-01225 INSP-Final Inspection9/7/19999/7/19999/7/1999 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 09/07/1999 at 10:49:17. Contact: ###-####.; 9/7 fire ok per 409. jrb;
BLD99-01192 INSP - Foundation9/7/19999/7/19999/7/1999 12:00:00 AMPPASS
Scheduled by a contractor via Hello! on 09/07/1999 at 08:08:22. Contact: ###-####. 9/7 Rebar OK, Ground rod OK. jrb
BLD99-02414 INSP - Final9/7/19999/7/19999/7/1999 12:00:00 AMPFAIL
WALT ###-####; 9/7 Engineer req 2x8 #2 of 24 oc, approved plan 2x6 of 240c, provide engineer for 2x6. jrb
BLD99-01468 INSP - Framing/Rough-in9/7/19999/7/19999/7/1999 12:00:00 AMPPASS
jason-- ###-#### cell -ceiling insp; Ceiling grid ok for cover. jrb