Inspections for the day of: Friday, September 7, 2007.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR07-00525 INSP-Final Inspection9/7/20079/7/20079/11/2007 9:04:56 PMPDEFR
See inspection comments completed 9/10.
FIR07-00441 INSP-Alarm Testing9/5/20079/7/20079/10/2007 1:31:14 PMAPART
EOL voltage drop at the office area is too low, one SD in the electrical room has an incorrect descriptor, incorrect cd at the receiving area amended while on site, retested noted defficiencies from the previous visit, highlighted locations on the first floor not yet complete for inspection including the elevator and cleanroom areas, noted ECS room staff is lacking for constant attendance as only one trained employee is provided at this time.
FIR07-00367 INSP-Sprinkler Rough-in9/7/20079/7/20079/7/2007 2:50:44 PMPPART
DP rough-in at the entry vestibule, head relocation and head change for the lobby including suite 110 are satisfactory, also inspected temp. ssu protection at suite 130, no access provided for the remainder of the building to verify head replacement completion.
BLD07-01014 FIRE-Final Inspection9/7/20079/7/20079/7/2007 2:12:15 PMPPART
The cardio, yoga, open weights, and reception areas are acceptable, noted approved door hardware is to be provided at the re-used existing doors including the yoga and kids rooms, missing one sprinkler escutcheon at the office, remodel east of the brick wall is not complete at this time.
BLD07-00642 FIRE-Final Inspection9/7/20079/7/20079/7/2007 1:47:21 PMPPASS
Fire life safety inspection passed.
FIR07-00203 INSP-Final Inspection9/7/20079/7/20079/7/2007 12:11:57 PMPPASS
Corrections accepted, fire sprinkler permit finaled.
FIR07-00191 FIR-Aging Inspection9/7/20079/7/20079/7/2007 12:10:20 PM DONE
Work in progress.
BLD06-01663 FIRE-Final Inspection9/6/20079/7/20079/7/2007 12:05:10 PMAPASS
Noted items required for compliance have been completed, fire life safety finaled.
BLD06-01483 FIRE-Final Inspection9/6/20079/7/20079/7/2007 11:58:42 AMAPASS
Verified required corrections, inspection passed.
FIR07-00680 INSP-Final Inspection9/7/20079/7/20079/7/2007 11:57:53 AMAPASS
Fire sprinkler permit finaled. Per contractor, an new permit for additonal work is pending.