PLM99-03074
| Plumbing Rough-in | 9/8/1999 | 9/8/1999 | 9/8/1999 12:00:00 AM | | PASS |
|
|
PAT-- ###-#### R/I; 9/8 entered pass. jrb
|
PLM99-03076
| Final | 9/8/1999 | 9/8/1999 | 9/8/1999 12:00:00 AM | | PASS |
|
|
Bill ###-####; 9/8 entered pass. jrb
|
PLM99-03044
| Sprinkler (Final) | 9/7/1999 | 9/8/1999 | 9/8/1999 12:00:00 AM | A | PART |
|
|
9/8 Underground ok. jrb
|
PLM99-03048
| INSP - Final | 9/3/1999 | 9/8/1999 | 9/8/1999 12:00:00 AM | A | PASS |
|
|
cecil ###-#### swr & water insp; 9/8 entered pass. jrb
|
PLM99-03044
| Sprinkler (Final) | 9/8/1999 | 9/8/1999 | 9/8/1999 12:00:00 AM | P | PASS |
|
|
MARY ###-####; 9/8 entered pass. jrb
|
PLM99-00773
| Final | 9/8/1999 | 9/8/1999 | 9/8/1999 12:00:00 AM | P | PART |
|
|
john ###-#### reinspection; 9/8 Temp occ PUB required pm emergency wash. jrb
|
PLM99-03027
| Plumbing Rough-in | 9/7/1999 | 9/8/1999 | 9/8/1999 12:00:00 AM | P | PASS |
|
|
TAMMY ###-#### RESCHEDULED; 9/8 entered pass. jrb
|
PLM99-03061
| Final | 9/7/1999 | 9/8/1999 | 9/8/1999 12:00:00 AM | P | PASS |
|
|
RITA ###-####, BACKFLOW; 9/7 cqtd order entry frm comp jrb; 9/8 entered pass. jrb
|
PLM99-03065
| Water and/or Sewer | 9/7/1999 | 9/8/1999 | 9/8/1999 12:00:00 AM | P | PASS |
|
|
###-####, READY AT 3:30; 9/8 Entered pass. jrb
|
PLM99-02207
| Final | 9/8/1999 | 9/8/1999 | 9/8/1999 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 09/08/1999 at 08:59:47. Contact: ###-####; 9/8 entered pass jrb.
|
PLM99-02713
| Final | 9/8/1999 | 9/8/1999 | 9/8/1999 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 09/08/1999 at 09:10:10. Contact: ###-####. 9/8 entered pass. jrb
|
PLM99-02736
| Final | 9/8/1999 | 9/8/1999 | 9/8/1999 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 09/08/1999 at 09:11:44. Contact: ###-####. 9/8 entered pass. jrb
|