FIR06-00367
| FIR-Aging Inspection | 9/8/2006 | 9/8/2006 | 9/15/2006 9:37:44 AM | | NR |
|
|
Per Charlie the work is complete, they are just waiting to get the st. als project completed first
|
FIR06-00641
| INSP-Sprinkler Rough-in/Hydro | 9/7/2006 | 9/8/2006 | 9/8/2006 4:53:29 PM | P | PASS |
|
|
Underground supply is ok to bury.
|
FIR06-00544
| INSP-Final Inspection | 9/7/2006 | 9/8/2006 | 9/8/2006 4:52:55 PM | P | PASS |
|
|
Sprinkler piping in hard lid areas in main lobby and the closets is ok to cover. A sign will be needed on ceiling tiles for elevator pit control valve location.
|
FIR06-00457
| INSP-Final Inspection | 9/7/2006 | 9/8/2006 | 9/8/2006 2:55:45 PM | P | PASS |
|
|
Permit finaled
|
FIR05-00272
| INSP-Sprinkler Rough-in/Hydro | 9/7/2006 | 9/8/2006 | 9/8/2006 2:36:36 PM | P | CANC |
|
|
No time for the hydro test today
|
FIR05-00403
| INSP-Sprinkler Rough-in | 9/7/2006 | 9/8/2006 | 9/8/2006 2:09:42 PM | P | FAIL |
|
|
The piping sizing in the end garage where the remote area is does not match plan. Plan shows 1" piping but 2" is installed. Also the 3rd floor remote area has a piping size problem as well and has been marked on the plans. No tenting has been done yet either. I gave Kennie permision to cover everything but the end garage and entire third floor until revised hydraulic calculations are provided and a tenting inspection is done.
|
FIR06-00616
| INSP-Sprinkler Rough-in | 9/7/2006 | 9/8/2006 | 9/8/2006 1:45:43 PM | A | PASS |
|
|
The remaining underground supply piping is ok to cover.
|
FIR06-00346
| INSP-Sprinkler Rough-in/Hydro | 9/5/2006 | 9/8/2006 | 9/8/2006 12:29:54 PM | A | FAIL |
|
|
Hydro test failed. Guage appeared to have lost 2-3 psi from 10:15am to 12:15pm.
|
BLD06-01488
| FIRE-Final Inspection | 9/7/2006 | 9/8/2006 | 9/8/2006 11:52:44 AM | A | FAIL |
|
|
See the original correction notice for remaining items that did not get corrected which include the repair of the exit sign at the north east exit door, mounting of the fire extinguishers and the correct sticker at the south main exit door.
|
FIR06-00617
| INSP-Sprinkler Rough-in | 9/7/2006 | 9/8/2006 | 9/8/2006 11:08:14 AM | A | PASS |
|
|
The remaining underground is ok for cover
|
FIR06-00361
| INSP-Final Inspection | 9/6/2006 | 9/8/2006 | 9/8/2006 9:26:43 AM | A | PASS |
|
|
Permit finaled
|
FIR06-00656
| INSP-Final Inspection | 9/7/2006 | 9/8/2006 | 9/8/2006 8:56:26 AM | A | PASS |
|
|
Permit finaled
|
FIR05-00724
| INSP-Final Inspection | 9/7/2006 | 9/8/2006 | 9/8/2006 8:55:05 AM | A | PASS |
|
|
Permit finaled. Contractor needs to install head guards on the sidewall heads
|
FIR06-00641
| INSP-Sprinkler Rough-in/Hydro | 9/7/2006 | 9/8/2006 | 9/7/2006 3:57:02 PM | A | CANC |
|
|
Contact: Todd - Cover Inspection; Phone #: ###-#### Internet Inspection Request from: Alicia Pauley Inspection cancelled from web by: Alicia Pauley
|