Inspections for the day of: Tuesday, September 8, 2009.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorBob Reichert
TitleELE-INSPECTOR
Phone #794-1923
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE09-01679 Electrical Rough-In9/8/20099/8/20099/8/2009 4:39:06 PMPPASS
Don Phone #: ###-#### ric ok, no esc this project
ESC09-00193 General Inspection9/8/20099/8/20099/8/2009 3:49:07 PMPPASS
looked ok
ELE09-01134 Final9/8/20099/8/20099/8/2009 3:47:50 PMPFAIL
Scheduled by a contractor via Hello! on 9/8/2009 at 8:38:14 AM. Contact: ###-####. met contractor, gave corrections as: BCC all fixtures shall be installed, NEC 210.52 shall install small appliance branch circuits per code, shall install convenience receptalces per code, shall install receptacles tightly
ELE09-00830 Final9/8/20099/8/20099/8/2009 3:28:23 PMPPASS
This is for a final inspection. Contact is Rey. Thank you and have a great day! Phone #: ###-#### Internet Inspection Request from: Laura Longshaw ok to final, no esc this project
ELE09-00829 Final9/8/20099/8/20099/8/2009 1:48:19 PMPPART
This is for a final inspection. Contact is Rey. Thank you and have a great day! Phone #: ###-#### Internet Inspection Request from: Laura Longshaw inspected by 412 and 370, ok to final office areas only, ok to move in furniture only, not people, no esc this project
ELE09-01616 Final9/4/20099/8/20099/8/2009 10:09:52 AMAPASS
shane - please call 1/2 hr prior Phone #: ###-#### met contractor, ok to final, no esc this project
ESC07-00703 Aging Inspection9/8/20099/8/20099/8/2009 9:35:47 AM DONE
looks ok, see site final
ESC07-00703 Site Final9/8/20099/8/20099/8/2009 9:35:34 AMPPASS
looks ok, ok to final
ESC07-00698 Site Final9/8/20099/8/20099/8/2009 8:44:33 AMAPASS
looks ok, ok to final
ESC07-00660 Site Final9/8/20099/8/20099/8/2009 8:14:31 AMAPASS
all work seems done, ok to final