Inspections for the day of: Monday, September 8, 2014.
Number of inspections: 4
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD14-02564 FIRE-Final Inspection9/8/20149/8/20149/8/2014 3:30:03 PMPFAIL
See the city approved plans for locations of corrections which include door hardware and fire extinguishers. Also plan reviewer needs to be contacted about the stairs/storage mezzanine that is not shown on the plans.
FIR14-00444 INSP-Sprinkler Rough-in9/8/20149/8/20149/8/2014 3:28:59 PMPFAIL
Tenting is incomplete. Piping can not be covered.
FIR14-00537 INSP-Sprinkler Rough-in/Hydro9/8/20149/8/20149/8/2014 2:36:20 PMPFAIL
Overhead hydro test failed due to visable drop in pressure on the guages.
BLD13-03382 FIRE-Final Inspection9/5/20149/8/20149/8/2014 10:41:12 AMAFAIL
All emergency lights and exit signs repaired. Life safety ok to final when the project related fire alarm system has corrections made