BLD03-01020
| BLD-Aging Inspection | 9/9/2008 | 9/9/2008 | 9/11/2008 10:24:25 AM | | CANC |
|
|
|
FIR08-00164
| INSP-Final Inspection | 9/9/2008 | 9/9/2008 | 9/10/2008 10:04:39 AM | P | FAIL |
|
|
Noted several spacing issues at the SW branch line adjacent to the overhead doors, missing PRV at the riser, trapeeze hanger at the last piece of 6" main is overspaced, FDC piping is missing hanger support and bracing at the vertical run, noted added head at the electrical room, provide riser tags, signage, DCVA certification, and complete forward flow testing in conjunction with riser supervision. Site inspection completed 9/9.
|
FIR08-00391
| FIR-Aging Inspection | 9/9/2008 | 9/9/2008 | 9/10/2008 7:42:00 AM | | DONE |
|
|
Work in progress, construction underway.
|
FIR08-00281
| INSP-Conference | 9/8/2008 | 9/9/2008 | 9/10/2008 7:41:13 AM | P | DONE |
|
|
On site visit regarding SW head locations and project scheduling.
|
FIR08-00474
| INSP-Sprinkler Rough-in | 9/9/2008 | 9/9/2008 | 9/10/2008 7:37:43 AM | P | PART |
|
|
OH rough-in is approved for cover at the TI drop ceilings.
|
FIR08-00587
| INSP-Final Inspection | 9/8/2008 | 9/9/2008 | 9/9/2008 2:41:45 PM | P | PASS |
|
|
Scope of work completed per plan, fire sprinkler permit finaled.
|
FIR08-00466
| INSP-Final Inspection | 9/8/2008 | 9/9/2008 | 9/9/2008 2:40:36 PM | P | PASS |
|
|
Upright sprinkler protection is acceptable pending the complete removal of the grid ceiling.
|
FIR08-00542
| INSP-Final Inspection | 9/8/2008 | 9/9/2008 | 9/9/2008 2:38:58 PM | P | FAIL |
|
|
Upright heads at one branch line do not meet obstruction tables per NFPA 13 8.6.5.1.2 due to adjacent ductwork.
|
FIR08-00163
| INSP-Final Inspection | 9/9/2008 | 9/9/2008 | 9/9/2008 11:47:05 AM | A | FAIL |
|
|
One upright head adjacent to the mech. room is too close to the wall, FDC piping needs a hanger on the horizontal piece and bracing/support for the vertical run, missing PRV at the riser, noted one added head at the electrical room. Riser needs calc. stickers, signage, backflow certification, forward flow test, and tamper/flow testing in conjunction with the fire alarm work.
|
BLD08-01879
| FIRE-Final Inspection | 9/8/2008 | 9/9/2008 | 9/9/2008 10:22:42 AM | A | FAIL |
|
|
Need to provide signage and approved hardware at the main entry/exit door per discussion and project review notes.
|