Inspections for the day of: Tuesday, September 9, 2008.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD07-03079 FIRE-Final Inspection9/9/20089/9/20089/9/2008 4:23:14 PMPCANC
Project is not ready fo the fire life safety inspection.
BLD07-03031 FIRE-Final Inspection9/9/20089/9/20089/9/2008 4:22:37 PMPCANC
Project is not ready fo the fire life safety inspection.
FIR08-00243 INSP-Final Inspection9/8/20089/9/20089/9/2008 3:54:28 PMPPASS
Permit finaled
FIR08-00529 INSP-Final Inspection9/9/20089/9/20089/9/2008 3:54:07 PMPFAIL
There were no approved plans on site and after a discussion with the technician a resubmittal is in order due to the reconfiguration of the initiation devices into the new fire alarm panel. They had been submitted as reporting to the addressable loop but are not utilizing the hardwired zones.
BLD08-01200 FIRE-Final Inspection9/9/20089/9/20089/9/2008 3:52:14 PMPFAIL
Provide 2A10BC fire extinguishers with current inspection tags, repair the east exit sign and provide a maximum 1/2" threshold at the office door.
FIR08-00504 INSP-Sprinkler Rough-in9/8/20089/9/20089/9/2008 11:34:12 AMAPASS
The remaining 6" underground supply is ok to cover and has been installed as per plans.
FIR08-00456 INSP-Final Inspection9/9/20089/9/20089/9/2008 11:20:41 AMAPASS
Permit finaled. Ceilings have been installed in the closets with pendants.