Inspections for the day of: Tuesday, September 9, 2014.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorDave Hannah
TitleBLD-COM/RES INSPECTOR
Phone #794-1967
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD13-02423 BLD-Concrete9/8/20149/9/20149/16/2014 8:37:02 AMPPASS
Level 2 podium deck pour inspection, Concrete deck pour is scheduled for 9/11 @ 1am Mike WIlson Phone #: ###-#### Inspection requested via web by Mike Wilson
MIS14-00186 BLD-Conference9/9/20149/9/20149/15/2014 2:31:39 PMACANC
Still no permit application submitted. Issue 5 day notice.
BLD14-00452 BLD-Wall Bracing9/9/20149/9/20149/10/2014 7:53:01 AMPPART
Kendle Phone #: ###-#### ok to cover roof and insulate freezer walls
BLD14-02556 BLD-Other9/9/20149/9/20149/9/2014 3:04:24 PMPNR
Daniel- block and tie down Phone #: ###-#### no paper work on site
BLD14-01185 BLD-Energy code compliance9/5/20149/9/20149/9/2014 2:37:38 PMPPASS
Grant Phone #: ###-####
BLD14-00148 BLD-Foundation9/8/20149/9/20149/9/2014 2:03:01 PMAPASS
Matt Phone #: ###-####
BLD14-00907 BLD-Footing9/9/20149/9/20149/9/2014 2:02:42 PMPNR
Ben Phone #: ###-#### needs geo signoff and install rebar
BLD14-01792 BLD-Wall Bracing9/8/20149/9/20149/9/2014 2:01:40 PMPFAIL
Chi Phone #: ###-####
BLD14-02273 BLD-Framing/Rough-in9/8/20149/9/20149/9/2014 10:40:39 AMAPASS
Ed Phone #: ###-####
BLD14-02254 BLD-Framing/Rough-in9/8/20149/9/20149/9/2014 9:07:06 AMAPART
Brad Phone #: ###-#### framing ok but needs elec roughed in and inspected first
BLD14-02254 BLD-Wall Bracing9/8/20149/9/20149/9/2014 9:06:17 AMAPASS
Brad Phone #: ###-####
MIS14-00171 MEC-Final9/8/20149/9/20149/8/2014 3:43:28 PMACANC
Call Max at job site for access. ###-#### Phone #: ###-#### >> Inspection requested via web by David Cole Inspection cancelled from web by: David Cole