ELE19-04228
| Electrical Rough-In | 8/4/2020 | 8/4/2020 | 8/4/2020 2:11:33 PM | P | PASS |
|
|
Screened- Mark Phone #: ###-#### Hard lids and wall rough in as marked and dated on contractor print. ok to cover
|
ELE20-01794
| Electrical Rough-In | 8/4/2020 | 8/4/2020 | 8/4/2020 1:15:49 PM | P | PASS |
|
|
2nd floor ceiling inspection for lighting clouds Phone #: ###-#### Inspection requested via web by Shane Lott "Cloud" area drop ceiling only ok to cover. Discussed partial final requirments. (All life safety items shall be completed)
|
ELE19-02250
| Final | 8/4/2020 | 8/4/2020 | 8/4/2020 12:47:18 PM | P | PASS |
|
|
Please call Chris to sign off for final. Thanks! Phone #: ###-#### Inspection requested via web by Rafael Castillo final ok
|
ELE20-01564
| Final | 8/4/2020 | 8/4/2020 | 8/4/2020 12:46:58 PM | P | PASS |
|
|
Remodel call about inspection type // David Phone #: ###-#### Final ok
|
ELE20-02723
| Temporary Service | 8/3/2020 | 8/4/2020 | 8/4/2020 12:13:41 PM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Ryan Wake t/s u/g n ok
|
ELE20-01356
| Conference | 8/4/2020 | 8/4/2020 | 8/4/2020 11:09:13 AM | P | DONE |
|
|
Screened-Marcelo Phone #: ###-#### Discussed requirments of final. All required lighting outlets shall be funtional. Ok to blank missing fictures as long as required outlet is functional.
|
ELE20-02731
| Rough-In Permanent Service | 8/4/2020 | 8/4/2020 | 8/4/2020 10:53:50 AM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Therrin Robertson rough in ok to cover p/s u/g n ok
|
ELE20-02732
| Rough-In Permanent Service | 8/4/2020 | 8/4/2020 | 8/4/2020 10:52:51 AM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Therrin Robertson rough in ok to cover p/s u/g n ok
|
ELE20-02663
| Electrical Rough-In | 8/3/2020 | 8/4/2020 | 8/4/2020 10:26:40 AM | A | PASS |
|
|
James *screened* Phone #: ###-#### Water bond in skimmer and corner bond only ok to cover
|
ELE20-02451
| Rough-In Permanent Service | 8/4/2020 | 8/4/2020 | 8/4/2020 10:19:08 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Troy Ballard rough in ok p/s u/g n ok
|
ELE19-01688
| Electrical Rough-In | 8/3/2020 | 8/4/2020 | 8/4/2020 9:40:17 AM | A | PART |
|
|
screened - service gear and transformers // Jamie Phone #: ###-#### Serfvice gear and transformers checked. Transformersok to cover, Waiting on Performance testing and AFCI rating.
|
ELE20-02497
| Electrical Rough-In | 8/3/2020 | 8/4/2020 | 8/4/2020 8:48:50 AM | A | FAIL |
|
|
walls only Phone #: ###-#### Inspection requested via web by Dave Brueggemann 11o.3B Insulated bushings shall be installed on MC a per instructions. 330.24 MC Bent to breaking point(Next to back door.) 300.4 MC shall not be secured within 1 1/4in from face of framing(Water heater and recep back office) 110.12 Opening shall be closed(Missing conduit or KO seal Hall 4 gang.) MC not completed to floor box junction point.
|