BLD18-01027
| BLD-Conference | 4/1/2020 | 4/8/2020 | | A | |
|
|
|
BLD20-00363
| BLD-Ceiling Grid Inspection | 4/9/2020 | 4/9/2020 | 4/9/2020 3:42:48 PM | P | PASS |
|
|
1 office. Phone #: ###-#### Inspection requested via web by Todd Landvatter
|
BLD18-02618
| BLD-Foundation | 4/9/2020 | 4/9/2020 | 4/9/2020 2:26:57 PM | P | PASS |
|
|
Robert *left voicemail, patio being enclosed** Phone #: ###-####. Verified existing foundation systen, installation of rigid insulation, floor framing and vapor barrier on top of slab. Also R30 insulation in floor. Ok to place floor decking and construct walls. inspection done on line via google duo.
|
BLD20-00822
| BLD-Wall cover | 4/9/2020 | 4/9/2020 | 4/9/2020 1:58:13 PM | P | PASS |
|
|
Screened- Phone #: ###-####
|
BLD18-04519
| BLD-Framing/Rough-in | 4/8/2020 | 4/9/2020 | 4/9/2020 1:21:34 PM | P | FAIL |
|
|
Building 10 Energy Seal, Fire Caulking ; Framing for Cover Phone #: ###-#### Inspection requested via web by Bob Goodwin. Complete fire caulking, fireblock fur out walls. Provide approved fix for missed bearing points on C3 trusses.
|
BLD20-01081
| BLD-Framing/Rough-in | 4/8/2020 | 4/9/2020 | 4/9/2020 11:38:00 AM | P | PASS |
|
|
Please call Sid ###-#### Phone #: ###-#### Inspection requested via web by Carissa Mattison
|
BLD19-02218
| BLD-Final | 4/9/2020 | 4/9/2020 | 4/9/2020 11:37:43 AM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by nate hutton
|
BLD20-00153
| BLD-Energy code compliance | 4/8/2020 | 4/9/2020 | 4/9/2020 11:12:07 AM | P | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Joel Hirtle Inspection cancelled from web by: Joel Hirtle
|
BLD20-00416
| BLD-Other | 4/8/2020 | 4/9/2020 | 4/9/2020 10:23:40 AM | A | DONE |
|
|
Rebar Phone #: ###-#### Inspection requested via web by Robert Carlton
|
BLD19-01080
| BLD - Request for Extension | 4/8/2020 | 4/9/2020 | 4/9/2020 9:50:19 AM | A | PASS |
|
|
Mike **Request for Extension** Phone #: ###-####. Ok for 90 day extension.
|
BLD19-04926
| BLD-Final | 4/8/2020 | 4/9/2020 | 4/9/2020 9:48:48 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Korey Hall
|
BLD19-04926
| DOC - Permit Finaled | 4/9/2020 | 4/9/2020 | 4/9/2020 9:48:39 AM | P | PASS |
|
|
All bedroom furnishings have been removed from attic space. Door has been removed and sheetrocked. All missing smoke detectors installed.
|
BLD20-01048
| BLD-Other | 4/8/2020 | 4/9/2020 | 4/9/2020 8:52:10 AM | A | DONE |
|
|
Inspection on a completed asphalt re-roof project. Phone #: ###-#### Inspection requested via web by Michael La Pointe
|
BLD20-01048
| DOC - Permit Finaled | 4/9/2020 | 4/9/2020 | 4/9/2020 8:52:01 AM | P | PASS |
|
|
All work appeared to be done in accordance with local codes and ordinances.
|
BLD20-00294
| BLD-Energy code compliance | 4/9/2020 | 4/9/2020 | 4/9/2020 8:50:01 AM | A | PASS |
|
|
Thank you Phone #: ###-#### Inspection requested via web by Allen Jones
|
BLD19-02021
| BLD-Foundation | 4/7/2020 | 4/9/2020 | 4/9/2020 12:00:00 AM | A | CANC |
|
|
*screened* - Request last of morning - Corey Phone #: ###-####
|