Inspections for the day of: Thursday, April 16, 2015.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorKatie Marron
TitleFIRE INSPECTOR
Phone #395-7809
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
NAF15-00008 INSP-Final4/15/20154/16/20154/16/2015 2:37:21 PMAPASS
Scope of work completed. Rough in and final inspections passed. Fire Sprinkler permit finaled.
NAF15-00008 INSP-Alarm Testing4/15/20154/16/20154/16/2015 2:36:03 PMACANC
Permit number and inspection type does not match scope of work.
BLD14-03056 FIRE-Final Inspection4/16/20154/16/20154/16/2015 1:23:24 PMPPASS
Completed inspection 4/16 in conjunction with TI permit.
BLD15-00071 FIRE-Final Inspection4/15/20154/16/20154/16/2015 1:21:41 PMPPASS
Fire Lifesafety passed. Verified previous correction notice items completed satifactory.
FIR13-00167 INSP-Sprinkler Rough-in4/15/20154/16/20154/16/2015 11:42:31 AMPNR
Not ready for inspection per phone conversation from Contractor. Pending PIV location determination.
FIR14-00815 INSP-Sprinkler Rough-in/Hydro4/15/20154/16/20154/16/2015 11:35:35 AMAPART
2hr Hydrostatic pressure test on Dry system # 2 on the 4th floor completed ok. System #2 is the small system.
BLD15-00639 FIRE-Final Inspection4/15/20154/16/20154/16/2015 11:09:10 AMAPASS
Fire Life Safety finaled
BLD14-03326 FIRE-Final Inspection4/15/20154/16/20154/16/2015 11:07:52 AMAPASS
Fire Lifesafety Finaled
FIR15-00211 INSP-Final Inspection4/15/20154/16/20154/16/2015 11:05:32 AMAPASS
Scope of work completed, roughin and final inspection pass. Permit Finaled.
FIR14-00866 INSP-Sprinkler Rough-in4/15/20154/16/20154/16/2015 10:20:07 AMAPART
Tenting at 4th flr at south end completed with the exception of rm 431 (not completed) and the exterior wall in shower enclosure at rm 432. One area in room 430 adjusted on site.