FIR14-00638
| INSP-Sprinkler Rough-in/Hydro | 8/12/2015 | 8/13/2015 | 8/13/2015 4:06:46 PM | A | CANC |
|
|
Not ready for FS U/G test today - Will reschedule for tomorrow. NOTE: This test will also hydrotest all of the standpipe risers in the building.
|
FIR13-00724
| INSP-Alarm Testing | 8/12/2015 | 8/13/2015 | 8/13/2015 4:05:00 PM | A | PART |
|
|
Fire alarm testing (continuation) for abaove grade SDs, FSD, HVAC shutdowns, rolldown doors (floors 4 & 5) elevator smoke guard doors,etc. Checked monitoring for alarms received - OK. Also checked exterior bell for waterflow alarms - tested OK.
|
FIR14-00890
| INSP-Final Inspection | 8/13/2015 | 8/13/2015 | 8/13/2015 12:55:44 PM | P | CANC |
|
|
Talked to alarm contractor and told him that we cannot start fire alarm testing, until fire sprinkler systems (dry and wet) are ready for testing, which should be another day or so as hydrotesting and air testing of systems is currently being performed. If all the hydrotests and air test pass without problems, then the sprinklers can be made ready for flow testing, tampers, trip test of DP valves, etc.
|
FIR15-00096
| INSP-Supply line flush | 8/12/2015 | 8/13/2015 | 8/13/2015 12:51:15 PM | A | PART |
|
|
24 hour air tested started for all (four) dry=pipe valves. Will retest in 24 hours to ensure system is ait tight.
|
FIR15-00096
| INSP-Sprinkler Rough-in | 8/12/2015 | 8/13/2015 | 8/13/2015 12:49:31 PM | A | CANC |
|
|
5th floor wet systems not ready for hydrotest. Canceled Appt.
|
FIR15-00096
| INSP-Sprinkler Rough-in/Hydro | 8/12/2015 | 8/13/2015 | 8/13/2015 12:47:55 PM | A | PART |
|
|
%th floor dry-pipe system hydrostatic test (North side). 200 psi @ 2hrs - PASSED NOTE: South side DP system for 5th floor hydrotested this morning - also PASSED
|
FIR15-00096
| INSP-Sprinkler Rough-in | 8/11/2015 | 8/13/2015 | 8/13/2015 11:54:07 AM | P | PART |
|
|
Rough to cover inspection for the entire 5th floor corridors, including elevator lobbies. OK to cover pipe in these areas. Actually inspected on 8/12 TW
|
FIR15-00096
| INSP-Sprinkler Rough-in/Hydro | 8/11/2015 | 8/13/2015 | 8/13/2015 10:37:12 AM | P | PART |
|
|
Hydrostatic test of two (2) wet pipe systems for the fourth floor - 200 psi @ 2hrs - PASSED. Actually tested on 8/12 TW.
|
FIR14-00890
| INSP-Final Inspection | 8/12/2015 | 8/13/2015 | 8/13/2015 6:56:47 AM | A | CANC |
|
|
As early as possible Phone #: 2089414511 >> Inspection requested via mobile web by Nathan Price Inspection cancelled via mobile web on Thursday, August 13, 2015.
|