FIR14-00890
| INSP-Final Inspection | 8/13/2015 | 8/14/2015 | 8/14/2015 4:13:04 PM | A | CANC |
|
|
Fire alarm testing not performed today. The contractor needed time to hunt down a few ground faults and other trouble signals that were on the FACP. Fire sprinklers were being put into service throughout the day. By the end of the day, all GFs and troubles were cleared, and the final dry pipe system was being put on line. Contrator agreed to pretest what he could before our inspection tomorrow (8/15).
|
BLD13-03405
| FIRE-Final Inspection | 8/14/2015 | 8/14/2015 | 8/14/2015 2:49:41 PM | P | PART |
|
|
Inspection to add two units on the fifth floor to TCO area (units 514 and 515). Fire sprinklers and fire alarm devices inspected and OK for these units. A temp. wall and door assembly to be constructed in the corridor to prevent residents from going into construction zone.
|
FIR14-00531
| INSP-Final Inspection | 8/14/2015 | 8/14/2015 | 8/14/2015 2:45:41 PM | P | PART |
|
|
Inspection of fire sprinklers for units 514 and 515 to add to TCO for the 5th floor of Tower 3. - OK to occupy these units.
|
FIR14-00875
| INSP-Final Inspection | 8/13/2015 | 8/14/2015 | 8/14/2015 2:41:40 PM | A | PART |
|
|
Fire alarm system testing of portions of Tower 3 5th floor (units 514 &515)) to add to TCO. Alarms for these units, and area of the corridor serving these units, are OK
|
FIR14-00638
| INSP-Final Inspection | 8/14/2015 | 8/14/2015 | 8/14/2015 1:30:49 PM | P | PASS |
|
|
Hydrostatic pressure test of the FS U/G supply line from the city connection to the A/S riser manilfold (200 psi @ 2hrs) PASSED Also hydrotested the bulk supply line to all of the building standpipe risers (200 psi @ hours) - PASSED.
|
FIR15-00096
| INSP-Final Inspection | 8/13/2015 | 8/14/2015 | 8/14/2015 1:27:34 PM | P | PART |
|
|
Completed 24 hour air tests of the two dry pipe valves protecting the attics (North and South) - PASSED. Also hydrotested the 5th floor wet pipe systems (200psi @ hours) - PASSED
|
FIR14-00687
| INSP-Final Inspection | 8/14/2015 | 8/14/2015 | 8/14/2015 1:24:42 PM | P | PART |
|
|
Completed 24 hour air tests of the two dry pipe valves for the parking garage. PASSED
|
BLD13-02424
| FIRE-Conference | 8/13/2015 | 8/14/2015 | 8/14/2015 11:52:37 AM | A | DONE |
|
|
Met with Elect. contractors to look at exit signage and emergency lighting for the 5 story bldg. Added a few exit signs in the parking garage to improve identification of egress paths, and added about 6/floor emergency lights in the corridors for the above floors.
|
BLD13-00016
| FIRE-Conference | 8/12/2015 | 8/14/2015 | 8/14/2015 11:49:40 AM | A | DONE |
|
|
Meeting with GC and electrical contractors to review upcoming exit signage and emergency lighting test, which will be scheduled for early morning (5am) to get an accuarte assessment of EMs under dusk conditions, since most of the egress from the building is outside, or open to the outside.
|