Inspections for the day of: Thursday, August 20, 2015.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorThomas Walsh
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD13-00016 FIRE-Final Inspection8/18/20158/20/20158/20/2015 4:57:10 PMPPART
Meeting to review egress plan prior to tomorrow'smeans of egress inspection with exit sigange and emergency lights off the generator.
BLD13-03405 FIRE-Final Inspection8/19/20158/20/20158/20/2015 3:37:08 PMAPART
Fire and Life-Safety inspection for use of Towers 3 & 4 corridors and stair 2 to egress these towers down to grade. Tested exit signs and EM lights for all floors - Tested OK. Two exit signs need to be added between Towers 2 & 3 at floors 2 and 3.
All stairwell doors and unit doors opening into the fire rated corridors for these two towers (all floors) need to be maintained closed and latched, in order to maintain the integrity of the corridor. GC talked to security to help maintain. Inspection of units for Tower 4 not completed yet.
FIR14-00875 INSP-Alarm Testing8/19/20158/20/20158/20/2015 3:30:46 PMPPART
Fire alarm inspection/test for Towers 3 & 4 corridors only - no unit inspections were conducted.
Test of MPs. SDs for FSDs, SDs for DH, etc, just within the corridors. Elevator for Tower 4 not ready for test. All devices tested satisfactorily within the corridors, and checked many units under general alarm.
FIR14-00430 INSP-Final Inspection8/19/20158/20/20158/20/2015 3:27:45 PMAPART
Fire sprinkler system inspection for Towers 3 & 4 - fire alarm interface only, i.e. tampers for standpipe control valves, and inspection of sprinklers for the corridors and stairwells serving Towers 3 & 4 - No unit inspections were conducted.
FIR14-00687 INSP-Final Inspection8/19/20158/20/20158/20/2015 10:44:32 AMPCANC
Revised plans for this permit have been submitted to Tim Frost for review prior to final sign off. Contractor will request final sign off after this review is completed.
FIR15-00096 INSP-Final Inspection8/19/20158/20/20158/20/2015 10:42:40 AMPCANC
Final inspection conducted through the 5th floor, on 8/19/15, however Records of Completion forms need to be submitted for all three (3) permits associated with this project. Contractor agreed to get paperwork together for signoff.
FIR14-00891 INSP-Final Inspection8/19/20158/20/20158/20/2015 10:36:48 AMAPASS
Completed fire alarm testing today, including a full test of the 5th floor corridors, and units.
Records of Completion paperwork filled out, signed off and submitted to the office.
NOTE: Some work in the building continues, that may cause dust (cleaning, sweeping, etc.). Contractor was advised to take necessary steps to prevent false alarms.
FIR14-00892 INSP-Final Inspection8/19/20158/20/20158/20/2015 10:35:51 AMAPASS
Completed fire alarm testing today, including a full test of the 5th floor corridors, and units.
Records of Completion paperwork filled out, signed off and submitted to the office.
NOTE: Some work in the building continues, that may cause dust (cleaning, sweeping, etc.). Contractor was advised to take necessary steps to prevent false alarms.
FIR14-00890 INSP-Final Inspection8/19/20158/20/20158/20/2015 10:35:01 AMAPASS
Completed fire alarm testing today, including a full test of the 5th floor corridors, and units.
Records of Completion paperwork filled out, signed off and submitted to the office.
NOTE: Some work in the building continues, that may cause dust (cleaning, sweeping, etc.). Contractor was advised to take necessary steps to prevent false alarms.