Inspections for the day of: Thursday, July 16, 2020.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR20-00361 INSP-Sprinkler Rough-in7/16/20207/16/20207/16/2020 4:09:17 PMPFAIL
Plans will need to be re-submitted to show use of flex drops in the grid ceiling. Add head where duct work is blocking coverage on first floor, notated on city approved drawing. Add sway brace that was not installed on level 2. Space under first floor stairs appears to be a combustible concealed pocket, if area is combustible then heads will have to be added or filled with non-combustilble insulation as discussed. Add upright head under duct work as notated on city approved drawings.

Please call Chris Ford Phone #: ###-#### Inspection requested via web by Jessia McLain
FIR20-00340 INSP-Conference7/16/20207/16/20207/16/2020 4:04:02 PMPDONE
Fire conference is complete. Advised Dustin with MCALVAIN too email Joe Bruce, Fire Section Supervisor too see if a variance can be granted to have the PIV closer than 40 feet to the building. PIV location was compromised due too fire truck access, PIV is no longer in the parking lot island as designed, island had to be shortened for fire truck access. A re-submittal will be required for underground supply re-route as noted on previous inspection and too show new location for PIV.
FIR20-00340 INSP-Sprinkler Rough-in7/16/20207/16/20207/16/2020 3:56:14 PMPCANC
Request was for a conference, this request is cancelled.

Screened- Dustin Phone #: ###-####
FIR19-00516 INSP-Sprinkler Rough-in7/15/20207/16/20207/16/2020 3:55:08 PMAPART
Rough to cover inspection for linen chute piping/heads complete, approved for cover.

Tony Cetani is the contact. Thanks! (: Phone #: ###-#### Inspection requested via web by Stan Beus
BLD19-04633 FIRE-Final Inspection7/16/20207/16/20207/16/2020 12:18:04 PMAPASS
Fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguishers are placed with current inspection tags, knox box is located by fire sprinkler riser room. Main entry and rear exit have mag locks installed as required by NFPA101 as well as state requirements for the type of use for this building. Mag locks do release on fire alarm activation and remain unlocked until fire panel is reset. Final life fire safety inspection is complete, signature card not available at time of inspection.
FIR20-00232 INSP-Final Inspection7/9/20207/16/20207/16/2020 12:09:30 PMAPASS
Previously noted items have been corrected, mag locks release on fire alarm activation.

Please call 20-30 minutes prior to inspection. You will be meeting technician Justin Volquardsen on site. Phone #: ###-#### Inspection requested via web by jason petty
BLD20-00111 FIRE-Conference7/15/20207/16/20207/16/2020 12:08:41 PMADONE
Fire conference is complete. A formal request for phased TCO plan will need to be submitted to the building code official as well as the fire code official for approval. All fire life safety items, too include fire alarm install and operation, will be required for the phased areas.

John- */Screened*/ Phone #: ###-####
FIR20-00295 INSP-Final Inspection7/15/20207/16/20207/16/2020 11:17:40 AMAPASS
Final fire sprinkler inspection is complete, irrigation was not installed but sprinkler timer was, wiring for irrigation shutdown was correct at time of inspection.

Call James before heading out, thank you! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
FIR19-00906 INSP-Supply line flush7/14/20207/16/20207/16/2020 9:31:03 AMADONE
Main line flush is complete.

Scheduled for 8:30am with Jim Page and Stacy with SUEZ. Call James if anything comes up. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
FIR20-00168 INSP-Sprinkler Rough-in7/13/20207/16/20207/16/2020 8:09:01 AMACANC
Cancelled per conversation with point of contact.

Richard Clark is the contact Phone #: ###-#### Inspection requested via web by Stan Beus
FIR19-00745 INSP-Final Inspection7/15/20207/16/20207/16/2020 8:08:00 AMAPART
Partial final inspection for fire alarms complete, notification inspection complete, sprinkler monitoring is complete, monitoring has been verified. Last remaining item to test is elevator recall and associated elevator items.

As early as possible Phone #: 2088990672 >> Inspection requested via mobile web by Josiah
FIR19-00623 INSP-Final Inspection7/15/20207/16/20207/16/2020 8:06:22 AMAPASS
Final fire sprinkler inspection is complete.

Phone #: ###-#### Inspection requested via web by Matthew Lewis
FIR20-00261 INSP-Sprinkler Rough-in7/15/20207/16/20207/15/2020 4:29:20 PMAPASS
Rough to cover inspection for underground supply complete, approevd for cover.

Bryan Collins is the contact. Thanks so much! (: Phone #: ###-#### Inspection requested via web by Stan Beus