FIR19-00491
| INSP-Conference | 7/20/2020 | 7/20/2020 | 7/20/2020 4:47:50 PM | P | DONE |
|
|
Conference complete with Andy, not the permit holder.
screened // Andy Phone #: ###-####
|
FIR19-00702
| INSP-Supply line flush | 7/17/2020 | 7/20/2020 | 7/20/2020 2:23:49 PM | P | DONE |
|
|
Re-flush on underground due too PIV addition has been complete.
Scheduling in case we can get everyone on board. Stacy is flexible on time, so please coordinate with James or Alicia so we can get Stacy out at your preferred time. ###-#### Thank you! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
FIR19-00516
| INSP-Sprinkler Rough-in/Hydro | 7/17/2020 | 7/20/2020 | 7/20/2020 2:20:03 PM | A | PART |
|
|
Hydrostatic test for level 1 wet system witnessed, no pressure loss observed at riser provided gauge.
Tony Cetani is the contact. This will be for the 1st floor Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR19-00516
| INSP-Sprinkler Rough-in | 7/17/2020 | 7/20/2020 | 7/20/2020 2:20:03 PM | A | PART |
|
|
Rough to cover inspection for level 1 hardlids complete, as well as grid area in kitchen and offices behind reception area, areas inspected approved for cover.
completeTony Cetani is the contact. This will be for the 1st floor Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR19-00702
| INSP-Sprinkler Rough-in/Hydro | 7/17/2020 | 7/20/2020 | 7/20/2020 11:42:00 AM | A | DONE |
|
|
PIV has been added, no pressure loss observed for re-hydro.
Underground rough/hydro - PIV has been installed on the fire line. Call James when heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
FIR20-00087
| INSP-Final Inspection | 7/20/2020 | 7/20/2020 | 7/20/2020 9:45:37 AM | A | PASS |
|
|
Final fire sprinkler inspection for scope of work is complete.
Phone #: ###-#### Inspection requested via web by Lonnie Greenfield
|
FIR19-00702
| INSP-Sprinkler Rough-in | 7/20/2020 | 7/20/2020 | 7/20/2020 9:11:13 AM | A | PASS |
|
|
PIV has been installed/inspected, cover is approved.
|
BLD19-00248
| FIRE-Final Inspection | 7/17/2020 | 7/20/2020 | 7/20/2020 9:07:10 AM | A | PART |
|
|
Life fire safety inspection for TCO phase 1 complete.
TCO Phone #: ###-#### Inspection requested via web by Chris Fuhrman
|