BLD19-01887
| BLD-Aging Inspection | 4/8/2020 | 4/8/2020 | 4/9/2020 8:48:14 AM | | PEND |
|
|
|
BLD19-01722
| BLD-Aging Inspection | 4/8/2020 | 4/8/2020 | 4/9/2020 8:47:49 AM | | PEND |
|
|
|
BLD19-02923
| BLD-Aging Inspection | 4/8/2020 | 4/8/2020 | 4/9/2020 8:46:41 AM | | PEND |
|
|
|
BLD20-00380
| BLD-Wall Bracing | 4/8/2020 | 4/8/2020 | 4/8/2020 3:16:51 PM | P | PART |
|
|
Randy **left voicemail** Phone #: ###-####//interior separation walls ok, two areas are gb braced wall panels ok per plans//
|
BLD19-00556
| BLD-Final | 4/7/2020 | 4/8/2020 | 4/8/2020 3:15:59 PM | P | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by Damion Jordan//CN issued//need to finish backfill around foundation on west and south side//need blower door test//need to post insulation certificate//need to complete shared driveway and turnaround or provide zoning approval//add house numbers to home//
|
BLD19-03656
| BLD-Framing/Rough-in | 4/8/2020 | 4/8/2020 | 4/8/2020 2:35:54 PM | P | FAIL |
|
|
Vence ** cleared** Phone #: ###-####//CN issued//previous wall bracing corrections have not been addressed//plans are missing 1/2 pages ripped some areas missing//need to provide engineering documents//previous corrections were marked in red on floors//complete inspection was not completed due to missing engineering/plans//
|
BLD19-04441
| BLD-Framing/Rough-in | 4/8/2020 | 4/8/2020 | 4/8/2020 1:11:01 PM | P | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover//need mechanical//see CN oniste//
|
BLD19-00323
| BLD-Conference | 4/8/2020 | 4/8/2020 | 4/8/2020 12:38:20 PM | P | DONE |
|
|
conference with contractor, mechanical contractor and inspectors, was scheduled under wrong permit//will need to have calcs and engineers approval and or fix for RTU units that have changed location and size, drawings including mechanical will need to be submitted for plan modification//
|
BLD19-00541
| BLD-Conference | 4/7/2020 | 4/8/2020 | 4/8/2020 12:07:34 PM | P | CANC |
|
|
*screened* - Ken Phone #: ###-####//scheduled under wrong permit//
|
BLD20-00875
| BLD-Footing | 4/7/2020 | 4/8/2020 | 4/8/2020 11:01:35 AM | A | PART |
|
|
Call before coming-Brian **cleared** Phone #: ###-####//ok when rebar is not touching earth, pad footing needs to bump out to 5 feet//setbacks appear to meet aproved plans//
|
BLD20-00656
| BLD-Ceiling Grid Inspection | 4/7/2020 | 4/8/2020 | 4/8/2020 11:00:32 AM | A | PEND |
|
|
Please call 30 mins ahead- Lloyd **cleared** Phone #: ###-####//ok, pending electrical isnpection for grid//
|
BLD19-04887
| BLD-Framing/Rough-in | 4/7/2020 | 4/8/2020 | 4/8/2020 10:11:36 AM | A | NR |
|
|
screened // nail pattern // Brett Phone #: ###-####//need to have shear plans/design match what is onsite//refered them back to designer to re calc the wall bracing accordingly//
|
BLD19-00064
| BLD-Ceiling Grid Inspection | 4/7/2020 | 4/8/2020 | 4/8/2020 9:07:22 AM | A | PASS |
|
|
*screened* - Jay Phone #: ###-####//music room grid ok//
|
BLD19-04441
| BLD-Framing/Rough-in | 4/7/2020 | 4/8/2020 | 4/8/2020 8:18:52 AM | A | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Kelly Stover Inspection cancelled from web by: Kelly Stover
|