PDS Online
Making
Boise
the most livable city in the country.
Home
Permits
Search by Permit Number
How to search by permit number
Search by Address
Search by Customer Number
Search by Current Planning Number
Search in Project by Permit Number
Search by Project Name
Inspections
Search by Permit Number
Search by Request Date
Search by Company Name
Fees
Impact Fees Estimate Calculator
Other Searches
Search for Licensed Contractors
Search Parcel by Address
Search Historical Surveys
Reports
Daily Reports
Weekly Reports
Monthly Reports
Home
/
Inspections
/
Inspector Activity
Inspections for the day of:
Monday, April 6, 2020
.
Number of inspections:
15
Percentage of inspections complete:
100 %
Percentage of inspections not complete:
0 %
Contact Information
Inspector
Andy J. Long
Title
EROSION INSPECTOR
Phone #
794-8996
Permit Number
Description
Received
Requested
Completed
AM/PM
Disposition
ESC20-00001
Complaint Inspection
4/3/2020
4/6/2020
4/6/2020 4:21:19 PM
A
PASS
dumping/stockpiling on 1724?
No dirt from site in road or gutter. Perimeter vegetation on lot has been preserved. Lot in question is planned to be construction of a new SFH that is in planning and approvals stage of project. Will continue to monitor.
Notified RP and parcel owner to make sure stockpiles do not causing sediment runoff or dust.
ESC18-01116
Aging Inspection
4/6/2020
4/6/2020
4/6/2020 3:52:51 PM
PASS
ESC18-01518
Aging Inspection
4/6/2020
4/6/2020
4/6/2020 3:52:14 PM
PASS
WIP. No ESC issues. Site contained and trash picked up.
ESC15-00853
General Inspection
4/6/2020
4/6/2020
4/6/2020 3:50:31 PM
PASS
No trackout or discharges from sub. WIP on west end foundations
ESC17-00954
General Inspection
4/6/2020
4/6/2020
4/6/2020 3:08:03 PM
PASS
No ESC issues, no corrections requests at this time. Disturbed areas have revegetated, some SFH construction is in progress. No recent excvations. Will need to remove DI bags at Bogust Basin once the Johnson house is complete.
ESC18-01455
General Inspection
4/6/2020
4/6/2020
4/6/2020 3:05:47 PM
PASS
No trackout or sediment runoff. WIP on home. No requests at this time.
ESC19-01188
General Inspection
4/6/2020
4/6/2020
4/6/2020 2:40:05 PM
P
PASS
ESC19-01415
General Inspection
4/6/2020
4/6/2020
4/6/2020 2:38:48 PM
P
PASS
ESC19-01569
Site Final
4/6/2020
4/6/2020
4/6/2020 2:38:24 PM
P
NR
Demo of home is complete. Brown Construction has lot to the west of this lot and will be using some dirt from a different site to make the ground level. Also need to remove all tires that were from the demolished shed.
ESC19-01188
General Inspection
4/6/2020
4/6/2020
4/6/2020 8:49:04 AM
P
CANC
ESC19-01387
DOC - Permit Finaled
4/6/2020
4/6/2020
4/6/2020 8:40:00 AM
P
PASS
demo complete, see ESC19-01415 for home construction
ESC18-00818
General Inspection
4/6/2020
4/6/2020
4/6/2020 8:17:18 AM
CANC
ESC19-00184
General Inspection
4/6/2020
4/6/2020
4/6/2020 8:08:37 AM
CANC
see ESC19-00839 & ESC19-00181 for inspection information on Village East Apartments
ESC19-00183
General Inspection
4/6/2020
4/6/2020
4/6/2020 8:08:23 AM
CANC
see ESC19-00839 & ESC19-00181 for inspection information on Village East Apartments
ESC19-00182
General Inspection
4/6/2020
4/6/2020
4/6/2020 8:08:05 AM
CANC
see ESC19-00839 & ESC19-00181 for inspection information on Village East Apartments